Logo Home   Documents and Lists   Create   Site Settings   Help   
Icon
Collin County Projects
2007 Transportation Bond Projects
 
 
 
Select a View
All Tasks
My Tasks
Due Today
Active Tasks
By Assigned To
General View
Administrative
 
 
Actions
  Alert me
  Export to spreadsheet
  Modify settings and columns
 
 
New New Item
|
Filter Filter
|
Edit in Datasheet Edit in Datasheet
 
Project IDManaging EntityProject NameFromToTypeProject DescriptionFilterLanes - ExistingLanes - ProposedOther Participating EntityEngineering Start DateEngineering End DateEngineering StatusConstruction Start DateConstruction End DateConstruction StatusCommentsFilterMapModified
Modified By
07-00-01Collin County
FM 2514
FM 2551FM 1378
Right-of-Way Only
COUNTY DISCRETIONARY PROJECT: Right of Way funding Participation with TxDOT.
$661,000.00
$661,000.00
7/6/2010: A funding agreement was approved in 2009. 10% local participation funding sent to TxDOT in April 2009.
THIS EFFORT FOR ROW participation is COMPLETE
 
This project funding also includes 1 parcel of land acquired by Collin County.
6/14/2011 2:08 PM
Tracy Homfeld
07-00-02Collin County
SH 289
@ US 380
Engineering Only
COUNTY DISCRETIONARY PROJECT: Engineering of the Intersection Improvment Project
$1,031,884.00
$1,031,884.00
COMPLETE
7/6/2010: County is funding both preliminary and final engineering for the TxDOT project. COMPLETE
 
RTR funds will be available for construction. Public Hearing to be held July 15, 2010. Construction let date scheduled for Nov 2010.
 
1/14/2011: CONSTRUCTION UPDATE - - - - Project has been let. Contractor to move in and start early February 2011.
 
11/14/2011: Verified by TxDOT onsite Engineer - CONSTRUCTION UPDATE - - - Will pour phase 1 of the bridge deck this week and are anticipating paving the last week in November or early December.  Contractor is anticipating switching traffic in the next phase sometime around the first of the year.  From there, the SB mainlanes and phase 2 of the bridge structure will be constructed and then completion of the NB mainlanes to the exit ramp on the South end of the project.
Estimated completion date is Summer 2012. 
CONSTRUCTION COMPLETE
11/20/2012 10:21 AM
Tracy Homfeld
07-00-03Collin County
Bloomdale Rd. Median opening
Engineering Only
COUNTY DISCRETIONARY PROJECT - Engineer a new median opening at Bloomdale Road and the Collin County Administration Building.
$5,000.00
$5,000.00
Engineering by CP&Y. COMPLETE
Construction done by Collin County Public Works
County Funded Engineering for New Median opening on Bloomdale Rd at County Administration Building. Construction done by County Public Works and is COMPLETE.
6/14/2011 2:09 PM
Tracy Homfeld
07-00-04McKinney
Ridge Road
Creekside Dr.US 380
Engineering and Construction
MCKINNEY REALLOCATED FUNDS PROJECT: This is a McKinney added project and  includes the design and construction of four lanes of Ridge Road from Creekside Drive to US 380.
 
This project is to facilitate a school opening in August 2010.
$1,442,228.00
$1,442,228.00
11/1/2009
3/31/2010
COMPLETE
4/1/2010
8/31/2010
Underway
6/21/2010: Verified by City - A design contract was awarded to HNTB Corp. in November 2009 for $430,000 and the design was completed in March 2010.  The construction contract was awarded to JRJ Paving in April 2010.  The project is on schedule for completion by August 2010 in order for the road to be open by the first day of school in mid-August.

 
9/1/2010: Verified by City Project Manager - Project is substantially COMPLETE and open to traffic.
9/27/2012 10:04 AM
Tracy Homfeld
07-00-05Collin County
SH 121
@ Exchange Intersection
Engineering and Construction
COUNTY DISCRETIONARY PROJECT - Local Govt. Participation in the re-design and construction of the SH 121 at Exchange Blvd intersection.
$10,354,187.00
$1,500,000.00
City of McKinney, City of Allen, NTTA
COMPLETE
COMPLETE
7/6/2010: The County participated funds ($1,500,000) in the re-design and construction of the interchange at SH 121 at Exchange.
PROJECT COMPLETE
6/14/2011 2:09 PM
Tracy Homfeld
07-00-06Collin County
FM 545
@ FM 1827
Right-of-Way Only
COUNTY DISCRETIONARY PROJECT: 10% Right of Way participation with TxDOT for reconstruction of the FM 545 at FM 1827 bridge.
$67,000.00
1/26/2011: Project is scheduled to be let in Oct. 2011 but this bond project for ROW is COMPLETE.
6/14/2011 2:09 PM
Tracy Homfeld
07-00-07Collin County
SH 78
Spring CreekSH 205
Right-of-Way Only
COUNTY DISCRETIONARY PROJECT: 10% Right of Way Participation with TxDOT for SH 78 from Spring Creek Parkway to SH 205. The county is paying the 10% participation for Wylie and Lavon using savinsg from past completed bond projects.
$200,002.00
1/2/2011: The Roadway construction project is scheduled to let in June 2012 but the ROW participation project is COMPLETE.
6/16/2011 4:42 PM
Tracy Homfeld
07-00-08Celina
SH 289
FM 1461FM 455
Right-of-Way Only
City of Celina's 10% Right of Way Particiaption with TxDOT.
$260,000.00
Funds have been sent to the City of Celina and those funds have been dispersed to TxDOT as per the City's Right of Way agreement.
COMPLETE
11/14/2011 12:36 PM
Tracy Homfeld
07-00-09Celina
SH 289
FM 455Business SH 289
Right-of-Way Only
City of Celina's Right of Way Participation with TxDOT for the SH 289 project froom FM 455 to Bus. SH 289.
$160,000.00
Funds have been sent to the City of Celina. Celina has dispersed funding to TxDOT per their Right of Way agreement.
COMPLETE
11/14/2011 12:55 PM
Tracy Homfeld
Attachment07-001Allen
Chaparral Bridge
Persimmon CourtBrook Ridge Ave
0.27
Engineering and Construction
Construct 2 lanes of the 4-lane Cottonwood Creek Bridge and fill in 2 lanes of the missing 4-lane divided gap (1400').
 
02
$2,160,000.00
$1,080,000.00
$1,080,000.00
2/8/2008
Complete
3/1/2010
5/31/2011
1/15/2010: Status verified by City of Allen - Design Complete. Currently acquiring Right of way. Anticipated construction start date is March 2010
 
6/21/2010: Verified by Project Technician City of Allen - Project under construction and should be complete by May 2011.
 
1/14/2011: Verified by City Engineer - Bridge opened December 2010, project substantially complete.  Final completion by May 2011. COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07001
6/14/2011 2:10 PM
Tracy Homfeld
07-00-10Collin County
SH 78
SH 205Business SH 78
Right-of-Way Only
COUNTY DISCRETIONARY PROJECT
City of Lavon's 10% Right of Way participation with TxDOT.
City to reimburse the county.
$130,000.00
Funds fronted by Collin County and been sent to TxDOT. The ROW particpation has been reimbursed by the City of Lavon.
COMPLETE
9/27/2012 10:05 AM
Tracy Homfeld
07-00-11Collin County
SH 78
Business SH 78FM 6
Right-of-Way Only
COUNTY DISCRETIONARY PROJECT: City of Lavon's 10% Right of Way Participation with TxDOT. City to reimburse the county.
$39,500.00
The funds were fronted by Collin County and sent to TxDOT. The City of Lavon has reimbursed the ROW funds.
COMPLETE
9/27/2012 10:06 AM
Tracy Homfeld
07-00-12Anna
FM 455
US 75.75 miles East of SH5
Construction Only
Reloaction of City owned Utilities, within the Right of Way of FM 455 from US 75 to .75 miles east of SH 5 in order to facilitate the widening of FM 455.
$1,600,000.00
$800,000.00
$800,000.00
11/14/2011: Funds have been sent to the City. Utility relocation engineering is underway. once all Right of Way is acquired by TxDOT, relocations can occur. Anticpated to be sometime in Spring 2012.
 
11/20/2012: Verified by City Manager - City is waiting on TxDOT permit. They expect to start in December 2012 and should be complete by the end June 2013. 
11/20/2012 10:43 AM
Tracy Homfeld
07-00-13McKinney
ALMA ROAD & SILVERADO TRAIL
Stacy Rd & Alma Rd.Fire Station #8 & Comstock Elementary
Engineering and Construction
CITY OF MCKINNEY REALLOCATED FUNDS PROJECT - This is an added project and includes design, right-of-way, and construction to widen Alma Road from Stacy Road to Fire Station #8 from two lanes to four lanes and to reconstruct Silverado Trail from Alma Rd. to Comstock Elementary as a four-lane divided roadway.  The 2007 County Bond Program budget is $1,523,676.
 
Funds were reallocated from existing McKinney Bond projects as follows:
#07-040: Airport Drive from US 380 to Industrial Blvd - $123,676
#07-037: FM 546 Replacement Preliminary Engineering from SH 5 to Airport Drive - $500,000
#07-038: Custer Road (FM 2478) Design and Right-of-Way from US 380 to FM 1461, $900,000
Total County participation of $1,523,676;
 
$1,523,676.00
$1,523,676.00
9/27/2012: Verified by City CIP Manager - Construction by Tiseo Paving is substantially COMPLETE
9/27/2012 10:05 AM
Tracy Homfeld
07-00-14Collin County
CR 419 @ Sister Grove
Engineering and Construction
Replace structurally deficient bridge.
Design survey is complete.  Plans are about 90% complete. 
4/16/2013 12:52 PM
Tracy Homfeld
07-00-15Collin County
CR 601 @ Tom Bean Creek
Engineering and Construction
Replace structurally deficient bridge.
Construction to begin Spring 2013
4/16/2013 12:53 PM
Tracy Homfeld
07-00-16Collin County
CR 132 @ Long Branch
Engineering and Construction
replace structurally deficient bridge.
Plans are 90% complete.  ROW obtained. Anticipate going out for bids in May 2013.
4/16/2013 12:55 PM
Tracy Homfeld
07-00-19McKinney
INTERSECTION CAPACITY IMPROV along Virginia Pkwy and El Dorado Pkwy
Engineering and Construction
CITY OF MCKINNEY REALLOCATED FUNDS PROJECT:
This added project includes design, right-of-way, and construction of right and dual-left turn lanes at seven intersections along Virginia Parkway and Eldorado Parkway:
• Virginia Parkway at Hardin Boulevard
• Virginia Parkway at Lake Forest Drive
• Eldorado Parkway at Hardin Boulevard
• Eldorado Parkway at Lake Forest Drive
• Eldorado Parkway at Ridge Road
• Eldorado Parkway at Alma Road
• Eldorado Parkway at Stonebridge Drive

The 2007 County Bond Program budget is $2,000,000. 
$4,008,700.00
$2,000,000.00
$2,000,000.00
9/27/2012: Verified by the City CIP Manager - Construction by Jim Bowman Construction is anticipated to be complete in December 2012. 
1/23/2013: Construction by Jim Bowman Construction is anticipated to be complete in February 2013. 
4/16/2013 1:02 PM
Tracy Homfeld
Attachment07-002Allen
Ridgeview Dr.
Custer Rd.Stacy Rd
1.84
Engineering and Construction
Add missing westbound lanes to the existing two eastbound lanes, construct missing 4-lane divided sections, and Construct northern half of the West Rowlett Creek Bridge and all six lanes of the Rowlett Creek Bridge.
 
04
$15,800,000.00
$7,900,000.00
$7,900,000.00
3/1/2009
Segment 1 Complete
6/21/2010: The City is looking at redefining scope to include the entire Ridgview cooridor from Custer to US 75.
 
Segment 1: Custer to Alma -
1/13/2009: Verified by City of Allen - Design is complete. 100% of Right-of-way acquired. CONSTRUCTION COMPLETE. OPENED NOV 2009.
 
Segment 2: Alma to Stacy Rd.:
6/21/2010: Verified by City of Allen Project Technician - City is doing an alignment study.
 
1/25/2013: Verified by City Engineer - Right-of-Way was acquired for the missing gap between Watters Branch Creek and Bray Central last year.  Design is currently being negotiated with Teague Nall & Perkins to construct at least a two lane connection with a bridge span over Watters Branch Creek.  When finished, this project would provide two, continuous lanes from Alma to Stacy.  City anticipates  a design contract with TN&P to be taken to City Council in February 2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07002
1/25/2013 1:05 PM
Tracy Homfeld
07-003Allen
Exchange Parkway
Exchange Overpassat SH 121
Engineering Only
Redesign and construct Exchange Overpass at SH 121 (6 lanes)
 
06
$900,000.00
$450,000.00
$450,000.00
PROJECT COMPLETED by the NTTA as part of the SH 121 Tollway project . The city is looking at reprogramming County funding. County approved discretionary funding for this so the bond funds will be reallocated.
http://maps.collincountytx.gov/bondrtr.html?pn=07003
6/14/2011 2:12 PM
Tracy Homfeld
07-004Allen
Bethany Dr.
Allen Heights Dr.Angel Pkway
1.53
Engineering and Construction
Add one east- and westbound lane to the existing 4-lane divided
46
$2,500,000.00
$1,250,000.00
$1,250,000.00
10/1/2010
6/30/2011
8/1/2011
7/1/2012
6/21/2010: Partial Funding programmed in 2010 is available now.
 
Confirmed by City Program Technician that the scheduled is undetermined at this point.
 
1/14/2011: Confirmed by City Engineer - Engineering started in October 2010 and is scheduled to be completed June of 2011. Construction estimated to begin in late summer 2011 and take approx 1 year.
 
4/20/2011: SAME AS ABOVE
 
1/25/2013: Verified by City Engineer - Roadway widening is COMPLETE and all six lanes are open to traffic.  Median restoration is under design and will be bid and under construction this spring.
 
http://maps.collincountytx.gov/bondrtr.html?pn=07004
1/25/2013 1:06 PM
Tracy Homfeld
Attachment07-005Allen
Watters Rd.
Bossy BootsRidgeview interchange
1.55
Engineering and Construction
Add two southbound lanes from Bossy Boots to Ridgeview Dr.
24
$2,600,000.00
$1,300,000.00
$1,300,000.00
1/1/2009
3/1/2009
Complete
6/1/2009
3/31/2010
Complete
Under construction by Mario Sinacola. Scheduled to be complete in early spring 2010
 
6/21/2010: Confirmed by City Program Tech. - PROJECT COMPLETE.
http://maps.collincountytx.gov/bondrtr.html?pn=07005
6/16/2011 4:42 PM
Tracy Homfeld
07-006Allen
Stacy Rd
Angel PkwyFM 1378
1.02
Construction Only
Reconstruct 2-lane roadway to a 4-lane divided
24
$980,000.00
$490,000.00
$490,000.00
RTR Funds for Construction
The City of Allen submitted Stacy Rd for RTR funds. They will use the 07 bond money as their 20% match for RTR Funding. 
 

1/12/2010: TxDOT is doing Engineering. Expect Environmental clearance in early 2010. Right-of-Way acquisition will start after that and should take 9-12 months. Construction to start by late 2010 or early 2011. The City will need to develop 3 party agreement with Fairview, Allen and Collin County.
 
6/21/2010: Confirmed by City Program Tech - TxDOT is doing Engineering. Awaiting Environmental clearance. Right-of-Way aquisition will start after that and should take 9-12 months.
 
1/18/2011: Verified by City Engineer and TxDOT - Public Hearing is scheduled for Feb. 24, 2011.
 
4/20/2011: Verified by City Engineer - TxDOT let date is Sept 2012.
 
1/25/2013: Verified by City Engineer -TxDOT to manage construction.  Currently TxDOT letting date is tentatively Dec 2014.  TxDOT ROW acquisition is underway. 
http://maps.collincountytx.gov/bondrtr.html?pn=07006
1/25/2013 1:07 PM
Tracy Homfeld
07-007Allen
US 75
Ridgeview Interchange
Engineering Only
Ridgeview Interchange (complete reconstruction with turn lanes and 6 through lanes)
28
$1,500,000.00
$750,000.00
$750,000.00
Engineering Complete
Funding programmed in 2011.
 
6/21/2010: Confirmed by City Program Tech - Project will more than likely be incorporated into the US 75 widening project. Schedule is undefined and dependent on funding.  
 
4/20/2011: SAME AS ABOVE
 
1/25/2013: Verified by City Engineer - Project will more than likely be incorporated into the US 75 widening project. Schedule is undefined and dependent on funding. 
 
 
http://maps.collincountytx.gov/bondrtr.html?pn=07007
1/25/2013 1:08 PM
Tracy Homfeld
07-008Allen
Ridgeview Dr.
Stacy RdUS 75
2.23
Engineering Only
Add missing westbound lanes to the existing two eastbound lanes, construct missing 4-lane divided sections, and Construct all six lanes of the Cottonwood Creek Bridge.
24
$2,060,000.00
$1,030,000.00
$1,030,000.00
6/1/2008
Completed Alighnment Study
1/12/2010: Teague Nall and Perkins is doing Engineering. Completed alignment study and are working on Right-of-way acquisition. Final Design will begin after ROW acquisition is complete. The City might want to look at all three phase of Ridgeview and restructure their agreements to allow engineering and land acquisition and using funds saved from the phased construction of Segment 1.
 
 
6/21/2010: Confirmed by City Project Tech - The City has completed an alighnment study and is working on Right-of-way aquisition. Final Design will begin after ROW aquisition is complete.  All county funding is available and is for Engineering only. No formal construction schedule established.
 
1/18/2011: Verified by City Engineer. Right of Way aquisition underway. No formal Construction schedule has been established.
 
1/25/2013: Verified by City Engineer - Right-of-Way was acquired for the missing gap between Stacy and Watters last year. The design is nearly complete on a four-lane linkage to connect the two dead-en sections, and will be bid next month. Construction will start in March or April and finish by the end of Summer 2013. Note: This construciton planned will not provide four continuous lanes to Stacy, but only build four-lanes where there is no roadway today (i.e. the "gap"). ROW acquisition continues on the segment, between Cottonwood Creek and US75.  working to get a proposal from an engineering consultant on design.  The goal is to have design completed by fall, with the ability to bid and start construction late this year. 
http://maps.collincountytx.gov/bondrtr.html?pn=07008
1/25/2013 1:11 PM
Tracy Homfeld
07-009Anna
Mantua Rd / CR 371
SH 5 (N. Powell Pkwy)US 75
1.89
Engineering and Construction24
$6,600,000.00
$3,300,000.00
$3,300,000.00
6-21-2010: Funding programmed in 2015.
http://maps.collincountytx.gov/bondrtr.html?pn=07009
6/21/2010 9:04 AM
Tracy Homfeld
07-010Anna
Rosamond Pkwy
SH 5 (N. Powell Pkwy)US 75
1.98
Engineering and Right-Of-Way24
$519,750.00
$259,875.00
$259,875.00
6-21-2010: Funding programmed in 2014.
http://maps.collincountytx.gov/bondrtr.html?pn=07010
6/21/2010 9:05 AM
Tracy Homfeld
07-011Anna
FM 455 (W. White St.)
US 75East Fork Creek
3.03
Engineering and Right-Of-Way24
$520,000.00
$260,000.00
$260,000.00
Funding is programmed in 2014.
http://maps.collincountytx.gov/bondrtr.html?pn=07011
6/21/2010 9:05 AM
Tracy Homfeld
07-012Anna
Ferguson Pkwy
FM 455 (W. White St.)Foster Crossing Rd.
1.70
Engineering and Right-Of-Way24
$594,000.00
$297,000.00
$297,000.00
Funding programmed in 2014.
http://maps.collincountytx.gov/bondrtr.html?pn=07012
6/21/2010 9:05 AM
Tracy Homfeld
Attachment07-013Carrollton
Midway Road
International PkwyHebron/Park Blvd.
0.46
Engineering and Construction
Addition of inside lanes to the existing 4-lane roadway to make a 6-lane divided roadway.
46
$1,213,287.00
$606,644.00
$606,644.00
6/1/2009
Complete
2/1/2010
10/31/2010
1/12/2010: Design is complete. Construction to start February of 2010 and should take 9 months.
 
6/21/2010: Confirmed by City Project Manager - Construction is 50% complete.
 
1/14/2011: Confirmed by City Project Manager - Construction is COMPLETE.
http://maps.collincountytx.gov/bondrtr.html?pn=07013
6/14/2011 2:08 PM
Tracy Homfeld
07-014Celina
CR 5
DNT ExtensionSH 289 (Preston Rd)
1.89
Engineering and Construction
Design and construct improvements to CR 5 from the DNT Extension to SH 289 from a 2-lane rural section to a 6-lane divided reinforced concrete street with integral monolithic concrete curbs and underground storm drainage designed to convey the 100-year storm frequency.
26
$10,003,000.00
$5,001,500.00
$5,001,500.00
12/1/2009
2/1/2011
Contract with BIRKHOFF, HENDRICKS & CONWAY, L.L.P. was approved on 11-9-09.
2/1/2012
7/31/2013
Past bond funds from #99-97 CR 56 ($242,000) and #03-121 CR 96 (235,404) were reallocated to fund cost over runs for this project.
 
The City has approved an Engineering contract with BIRKHOFF, HENDRICKS & CONWAY, L.L.P. BHC should start engineering work by Dec. 1, 2009.
 
6/21/2010: Verified by City Manager - Engineering is ongoing and should be completed by Sep. 1, 2011 (15months). Construction schedule is unknown due to funding constraints.

 
2/7/2011: Verified By City Manager - Design is ongoing.
 
1/23/2013: Verified by city Public Works Director - Design will proceed in 2013. The project was granted RTR funds for construction.
http://maps.collincountytx.gov/bondrtr.html?pn=07014
1/23/2013 9:45 AM
Tracy Homfeld
07-015Dallas
Preston Rd.
FrankfordLloyd Circle
0.47
Construction Only68
$1,925,000.00
$962,500.00
$962,500.00
1/1/2011
City's match will not be available until its next bond program in 2010 or early 2011. No county funding programmed until 2012.
 
6/21/2010: No change to schedule.
 
11/15/2011: Verified by City Engineering Dept. - City is looking at reallocating funds to another project.
http://maps.collincountytx.gov/bondrtr.html?pn=07015
11/15/2011 1:38 PM
Tracy Homfeld
07-016Fairview
Stacy Rd
FM 1378Ashcroft Dr.
1.30
Engineering and Construction
Widening from 2 to 4 lanes
23
$3,000,000.00
$1,500,000.00
$1,500,000.00
7/1/2008
7/1/2009
City has requested that Stacy Rd funds be reallocated to Fairview Parkway. Reallocation will be done at the time an Interlocal Agremeent is done for Fairview Parkway project #07-019. 
 
We sent the city $200,000 for this project. Remaining funds will be reallocated.
http://maps.collincountytx.gov/bondrtr.html?pn=07016
6/14/2011 2:13 PM
Tracy Homfeld
07-017Fairview
FM 1378
Lucas BoundaryFarmstead
1.00
Engineering and Right-Of-Way24
$425,000.00
$212,500.00
$212,500.00
7/1/2009
Funding is scheduled in 2011.
 
6/14/2011: Collin County and Fairview are sharing the cost of Preliminary Engineering for the section of FM 1378 from Farmstead to South of Stacy Rd. Collin County is managing the Engineering Contract. Public Meeting is being scheduled. This project is being Engineered in conjunction with the TxDOT managed contract for FM 1378 from South of Stacy Rd. to White Rock Creek.
 
11/16/2011: Stakeholder Cities have expressed an interest to stop work on this project therefore no further Engineering will be done.
http://maps.collincountytx.gov/bondrtr.html?pn=07017
11/16/2011 12:57 PM
Tracy Homfeld
07-018Fairview
Frisco Rd.
FM 1378Medical Center
0.22
Funds from the 2007 Bond Program are for Engineering adn Right-of-Way Only.
24
$250,000.00
$125,000.00
$125,000.00
7/1/2010
Bond Funding programmed in 2012.
http://maps.collincountytx.gov/bondrtr.html?pn=07018
6/14/2011 2:15 PM
Tracy Homfeld
07-019Fairview
Fairview Parkway
Ridgeview Dr.SH 5
1.00
Engineering and Construction
New Arterial - 4 Lane Divided
04
$3,200,000.00
$1,600,000.00
$1,600,000.00
7/1/2011
7/1/2012
Bond Funding programmed in 2012-2014.
http://maps.collincountytx.gov/bondrtr.html?pn=07019
7/6/2010 12:33 PM
Tracy Homfeld
07-020Farmersville
Ext. of Farmersville Pkwy (CR 611)
SH 78US 380
1.27
Engineering and Construction
Extension of Farmersville Parkway, west 6,700 lf, four lane divided thoroughfare, from SH 78 to US Hwy 380 along City of Farmersville’s Old McKinney Rd to CR 610 to CR 611.
24
$3,800,000.00
$1,900,000.00
$1,900,000.00
1/1/2008
Engineering Plans are at 95%
Right-of-Way Aquisition on going.
2008 Funds of $225,000 have been dispersed to the city.
PROJECT ON HOLD 
 
7/6/2010: 2010 Funding is available now. City is looking at completing Right of Way acquisition in 2010-2011.
 
1/19/2011: Verified by City Public Works Director - No Progress since last update.
 
5/9/2011: SAME AS ABOVE
 
11/15/2011: Verified by Consulting Engineer for the City - Plans are about complete and the city has purchased some of the Right of Way. Due to delays in developments this project remains on hold. Future county funding has been pushed to 2013 at this time.
http://maps.collincountytx.gov/bondrtr.html?pn=07020
11/15/2011 1:51 PM
Tracy Homfeld
07-021Farmersville
Extension of Floyd St
US 380Old Josephine Rd.
0.76
Engineering Only
Bond Funds for Engineering and Right-of-Way Only.
Extension of Floyd Street, south 4,000 lf, two lane thoroughfare, from US Hwy 380 to Old Josephine Rd.
02
$200,000.00
$100,000.00
$100,000.00
6/1/2008
Preliminary Layout and construction cost estimates have been completed.
2008 Funds of $25,000 have been sent to the City.
PROJECT ON HOLD
 
1/19/2011: Verified by City Public Works Director. No progress on this project.
 
5/9/2011: SAME AS ABOVE
 
11/14/2011: Verified by City Consulting Engineer - SAME AS ABOVE
http://maps.collincountytx.gov/bondrtr.html?pn=07021
11/15/2011 1:52 PM
Tracy Homfeld
Attachment07-022Frisco
Rolater Rd.
Independence PkwyCuster Rd.
1.00
Engineering and Construction
Construct 2 westbound lanes and bridge over Rowlett Creek to complete 4 lane divided urban roadway.
24
$4,015,000.00
$2,007,500.00
$2,007,500.00
2/19/2008
9/7/2010
Design is Complete.
9/7/2010
9/30/2011
60% Complete
2008 Funding Interlocal Agreement approved on 2-23-09.  2009 Funding Interlocal Agreement approved on 9-14-09
 
6/8/2010: Confirmed by Frisco Eng. Dept - Engineering is 99% Complete. Will bid for construction in July or August. Construction to take 11 months ad be completed May 2011.
 
1/3/2011: Confirmed by Frisco Eng. Dept  - Construction is 30% complete. Should be complete by August 2011.
 
4/19/2011: Confirmed by Frisco Eng. Dept  - Construction is 60% complete. Should be complete by September 2011.
 
9/12/2011: Confirmed by Frisco Eng. Dept. Construction Complete.
 
 
http://maps.collincountytx.gov/bondrtr.html?pn=07022
1/25/2013 11:15 AM
Tracy Homfeld
07-023Frisco
Coit Rd.
Main St.Panther Creek Pkwy
2.50
Engineering and Construction
Widen Coit Rd. to 4 lane urban divided roadway.
 
SEGMENT 1 -  From Main to N. of El Dorado: Widen from 2 to 4 lanes
 
SEGMENT 2 -  From 1/2 mile N. of El Dorado to Panther Creek Pkway: construct 4 lanes
24
$8,825,000.00
$4,412,500.00
$4,412,500.00
SEGMENT 1 - Coit from Main to North of ElDorado:
 
1/4/2011: Design is 60% complete.  Engineering was completed when previous Coit Rd project south of Main was done.  City is updating the plans and including them with the TxDOT FM 3537 project.  This part of Coit will get done with FM 3537.  City will execute an agreement with TxDOT to pay for our part of the project.  Construction on FM 3537 is expected to begin in Late 2011.
 
4/19/2011: Confirmed by Frisco Eng. Dept - Same as above
 
11/15/2011: Construction will begin Spring 2012
 
1/25/13:  Has been bid and will begin March 4, 2013. Estimated completion date is Oct 2013.
 
SEGMENT 2 - From 1/2 mile N. of El Dorado to Panther Creek Pkway:
 
1/4/2011: City has not begun engineering on this portion of Coit and currently do not have any plans to start.

4/19/2011: Confirmed by Frisco Eng. Dept - Same as above
 
11/16/2011: Confirmed by Frisco Eng. Dept - Engineering is expected to begin in early 2012. 
 
1/25/2013: Confirmed by Frisco Eng. Dept.  - Design is 90% Complete
http://maps.collincountytx.gov/bondrtr.html?pn=07023
4/8/2013 1:35 PM
Tracy Homfeld
07-024Frisco
El Dorado Pkwy
Panther CreekCuster Rd.
2.70
Engineering and Construction
Widen El Dorado Parkway from a 2 to 6 lane divided urban Roadway
 
From Panther Creek to Hillcrest: Widen from 4-6 lanes
 
From Hillcrest to Castleman Creek: Widen from 2-6 lanes
 
From Castleman Creek to Custer: Widen from 4-6 lanes
26
$8,695,000.00
$4,347,500.00
$4,347,500.00
3/2/2010
6/30/2011
60%
2/28/2012
4/30/2013
6/08/2010: The city is engineering the entire limits and have fronted the engineering money to get things moving.  Engineering should be completed in June 2011.  Construction start date dependent on County funding.
 
1/4/2011: Verified by City Eng. Dept - Engineering is approx. 60% Complete.
 
4/19/2011: SAME AS ABOVE
 
11/16/2011: Verified by City Eng. Dept. -Design should be completed by the end of the year.
 
1/25/2013: Verified by City Eng. Dept. Notice to proceed for construction was given on 1-14-2013. Estimated completion is Nov. 2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07024
1/25/2013 11:21 AM
Tracy Homfeld
Attachment07-025Frisco
Independence Pkwy.
Main St.North City Limits
2.00
Engineering and Construction
Widen Independence Pkwy from 2 to 4 lane divided urban roadway.
24
$5,140,000.00
$2,570,000.00
$2,570,000.00
2/2/2010
2/28/2011
COMPLETE
Funding ($2,570,000) ILA was approved on 11-16-09.
 
1/12/2010: Confirmed by City Eng. Dept - The City is beginning the scoping process for the Engineering contract.
 
6/8/2010: Confirmed by City Eng. Dept.  - Design is approximately 35% complete. Construction to begin Fall 2010.
 
01/04/2011: Confirmed by City Eng. Dept.  - Design is approximately 95% complete. Construction to begin March 2011.
 
4/19/2011: Confirmed by City Eng. Dept. - Design complete.  Project expected to bid in June 2011
 
9/12/2011: Confirmed by City Eng. Dept. - Construction began on Sept. 6, 2011.
 
1/25/2013: Verified by City Eng. Dept. - Construction is COMPLETE.
http://maps.collincountytx.gov/bondrtr.html?pn=07025
1/25/2013 11:22 AM
Tracy Homfeld
07-026Frisco
Coit Rd.
Panther Creek PkwyUS 380
2.20
Engineering and Construction
Construct Coit Rd. as a 6 lane divided urban roadway.
06
$10,340,000.00
$5,170,000.00
$5,170,000.00
1/1/2010
12/1/2010
1/1/2011
8/1/2012
Funding programmed in 2012
http://maps.collincountytx.gov/bondrtr.html?pn=07026
1/4/2011 3:12 PM
Tracy Homfeld
07-027Frisco
Virgina Pkwy. (Renamed to Rockhill Road)
DNTPreston Rd.
1.20
Engineering and Construction
Construct Rockhill Road as a 6 lane divided Urban Roadway.
06
$13,105,000.00
$6,552,500.00
$6,552,500.00
5/6/2008
1/31/2012
60%
2/22/2013
7/31/2014
6/08/2010: Confirmed by City Project Engineer - Engineering is at 60% complete. Should be completed Summer 2011. Construction schedule is unknown due to funding constraints.
 
01/04/2011: Confirmed by City Project Engineer - Engineering is at 60% complete.
 
4/19/2011: SAME AS ABOVE
 
11/15/2011: Engineering is on hold at 60% because Construction schedule is unknown due to funding constraints.
 
1/25/2013: Verified by City Eng. Dept. - Project has been bid and construction will begin in Feb 2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07027
1/25/2013 11:30 AM
Tracy Homfeld
07-028Frisco
Virgina Pkwy. (Renamed to Rockhill Road)
CR 26DNT
0.70
Engineering and Construction
Construct Rockhill Road as a 6 lane divided Urban roadway.
06
$5,406,000.00
$2,703,000.00
$2,703,000.00
5/6/2008
1/31/2012
60%
2/22/2013
7/31/2014
6/08/2010: Confirmed by City Project Engineer - Design is at 60% complete.
 
01/04/2011: Confirmed by City Project Engineer - Design is at 60% complete.
 
4/19/2011: SAME AS ABOVE
 
11/15/2011: Engineering is on hold at 60% because construction schedule is unknown due to funding constraints.
 
1/25/2013: Verified by City Eng. Dept. -Project has been bid and construction will begin in February 2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07028
1/25/2013 11:29 AM
Tracy Homfeld
Attachment07-029Frisco
El Dorado Pkwy
DNTFrisco St.
0.40
Engineering and Construction
Widen El Dorado Parkway from 4 to 6 lane divided Urban roadway.
46
$702,000.00
$351,000.00
$351,000.00
6/6/2006
4/1/2009
COMPLETE
6/1/2009
1/1/2011
COMPLETE
Interlocal Agreement has been approved. Design is complete. 
 
6/08/2010: Confirmed by City Project Engineer - Construction is approx. 70% complete. Construction to be completed by end of 2010.  
 
01/04/2011: Confirmed by City Project Engineer - Construction is COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07029
6/16/2011 4:47 PM
Tracy Homfeld
Attachment07-030Frisco
El Dorado Pkwy
FriscoPreston Rd.
1.80
Engineering and Construction
Widen El Dorado Parkway to 6 lane divided urban roadway.
46
$3,350,000.00
$1,675,000.00
$1,675,000.00
6/6/2006
4/1/2009
Complete
6/1/2009
1/1/2011
COMPLETE
Interlocal Agreement has been approved. Design is complete.
 
6/08/2010: Confirmed by City Project Engineer - Construction is approx 70% complete. Should be completed by end of 2010.

01/04/2011: Confirmed by City Project Engineer - Construction is COMPLETE. 
http://maps.collincountytx.gov/bondrtr.html?pn=07030
6/16/2011 4:47 PM
Tracy Homfeld
07-031Frisco
Virgina Pkwy. (Renamed to Rockhill Road)
Preston Rd.Coit Rd.
2.00
Engineering and Construction
Reconstruct existing 2 lane asphalt roadway to 6 lane divided urban roadway.
06
$13,500,000.00
$6,750,000.00
$6,750,000.00
Funding scheduled in 2014
http://maps.collincountytx.gov/bondrtr.html?pn=07031
6/21/2010 10:13 AM
Tracy Homfeld
07-032Frisco
Lebanon Rd.
County LineCoit Rd.
5.00
Engineering and Construction
Widen Labanon Rd. from 4-6 lanes.
46
$8,862,000.00
$4,431,000.00
$4,431,000.00
3/1/2011
Funding scheduled in 2015
http://maps.collincountytx.gov/bondrtr.html?pn=07032
6/21/2010 10:12 AM
Tracy Homfeld
07-033Frisco
North Dallas Parkway
WarrenEl Dorado Pkwy.
5.20
Engineering and Construction
Widen Northbound and Southbound frontage roads from 2 to 3 lanes.
46
$11,665,000.00
$5,832,500.00
$5,832,500.00
Funding scheduled in 2016
 
http://maps.collincountytx.gov/bondrtr.html?pn=07033
6/21/2010 10:13 AM
Tracy Homfeld
07-034Lucas
Country Club
West Lucas Road
Engineering and Construction
Intersection Improvements: FM 1378 (Country Club Rd) at West Lucas Rd. and at Estates.
 
At the W Lucas Rd and Country Club Rd (FM 1378) intersection; adding two turn lanes; westbound to northbound and southbound to westbound.
 
At the Country Club and Estates Parkway (FM 2170) intersection; adding one turn lane; southbound to westbound.
 
$500,000.00
$250,000.00
$250,000.00
2/1/2009
7/30/2009
CONSTRUCTION COMPLETE.
http://maps.collincountytx.gov/bondrtr.html?pn=07034
1/12/2010 2:21 PM
BONANZA\gabriela
Attachment07-035McKinney
Custer Rd.
Stonebridge Dr.US 380
3.50
Engineering and Construction
This project includes the design and construction of six lanes of Custer from Stonebridge Drive to US 380.
26
$5,000,000.00
$2,500,000.00
$2,500,000.00
COMPLETE
8/1/2009
9/30/2012
COMPLETE
12/12/09: Verified with City Engineer
Construction is being managed by TxDOT. Construction contract was awarded to Mario Sinacola and began summer 2009. Utility relocation is nearing completion.
 
6/21/2010: Verified by City - Roadway Design adn Utility relocation are completed. Construction contract award to Mario Sinacola and began in Aug 2009 and expected to be completed by June 2012.
 
1/18/2011: Verified by City CIP Manager - construction managed by TxDOT. Design Complete. Utilities relocation Complete. Construction began Aug 2009 and is expected to be completed by September 2012.  
 
6/14/2011: Verified by City Engineer. Roadway design and the relocation of utilities are both complete.  The construction is being managed by TxDOT.  The construction contract has been awarded to Mario Sinacola.  Construction began in August 2009 and is expected to be completed in April 2012.
 
11/14/2011: Verified by City CIP Manager - Same as above.
 
9/27/2012: Verified by CIP Manager - Construction by TxDOT resources is substantially complete.  City is waiting on TxDOT to reconcile the project and return unused local funds, if any.
 
http://maps.collincountytx.gov/bondrtr.html?pn=07035
9/27/2012 9:06 AM
Tracy Homfeld
07-036McKinney
FM 543 / FM 1461 Connector
US 75FM 1461 / Lake Forest
2.50
Engineering and Construction
Design and Construction of two lanes of a connection between FM 1461 and FM 543 (known locally as the FM 543 Connector).
04
$19,000,000.00
$9,500,000.00
$9,500,000.00
1/1/2009
10/1/2011
Engineering contract awarded to NDM in January 2009.
11/1/2010
Due to limited availability of funding the construction schedule is being re-evaluated by the city.
12/12/09: Verified with City Engineer:
The scope of the project has been reduced and the design is anticipated to be completed Fall 2011.
 
6/21/2010: Verified by City - Same as above. City is using sold bond funds to fund projects that are ready now. Will reallocate funding back when this project is ready.
 
1/18/2011: Verified by City CIP Manager - Design awareded in Jan 2009 and should be complete Fall 2011.
 
6/14/2011: Verified by City CIP Manager - The design contract for the project was awarded to NDM in January 2009.  The scope of the project has been reduced and the design of the revised project is anticipated to be complete in early 2012.  Construction to realign the intersection with US 75 will occur in 2012, in coordination with the TxDOT construction on US 75.
 
11/14/2011: Verified by City CIP Manager - Same as above

9/27/2012: Verified by City CIP Manager - The design contract for the project was awarded to NDM in January 2009.  The scope of the project has been reduced and the design of the revised project is anticipated to be complete in late 2012.  Construction to realign the intersection with US 75 will occur in 2013, in coordination with the TxDOT construction on US 75.   
http://maps.collincountytx.gov/bondrtr.html?pn=07036
9/27/2012 9:11 AM
Tracy Homfeld
Attachment07-037McKinney
FM 546 Replacement Route
SH 5Airport Dr.
1.70
Engineering and Right-Of-Way
This project involves the preliminary elements (environment assessment, schematic, right-of-way map) for four lanes of a replacement route for FM 546 from SH 5 to Airport Drive.    Upon completion of the construction, this project will provide improved access to the area surrounding the Collin County Regional Airport.
$2,000,000.00
$1,000,000.00
$1,000,000.00
4/1/2009
Preliminary Engineering Design contract awarded to Civil Associates.
N/A
12/11/2009: Verified by City Engineer:
A LPAFA is also being negotiated with TxDOT and is anticipated to be ready at the same time.  The LPAFA will outline all elements of the project  FONSI is anticipated to be received in March 2011.
 
6/21/2010: Verified by City - Prelim. Engineering contract awarded to Civil Associates. A draft LPAFA is being prepared by TxDOT. FONSI anticipated to be received in March 2011.
 
1/18/2011: Verified by City - Prelim. Engineering contract awarded to Civil Associates. A draft LPAFA is being prepared by TxDOT. FONSI anticipated to be received in March 2012.
 
6/14/2011: Verified by city CIP Manager - The preliminary engineering contract for the project was awarded to Civil Associates in April 2009. The schematic and draft environmental assessment were submitted to TxDOT for review in May 2011.   Environmental approval is anticipated to be received in March 2012.
Final Design and Construction to be managed by TxDOT.
 
11/14/2011: Verified by city CIP Manager -  The schematic and environmental assessment were submitted to TxDOT Austin for review in November 2011.   Environmental approval is anticipated to be received in the second half of 2012.
 
9/27/2012: Verified by city CIP Manager -The preliminary engineering contract for the project was awarded to Civil Associates in April 2009. The schematic was approved by TxDOT in December 2011.   Environmental approval is anticipated to be received in December 2012. 
http://maps.collincountytx.gov/bondrtr.html?pn=07037
9/27/2012 9:12 AM
Tracy Homfeld
07-038McKinney
Custer Rd.
US 380FM 1461
3.10
Engineering and Right-Of-Way
This project includes the design and Right-of-Way aquisition for four lanes of Custer Rd. from US 380 to FM 1461.
$5,000,000.00
$2,500,000.00
$2,500,000.00
1/1/2009
Design Contract awarded to KCI in January 2009 and is scheduled to be complete in 2013.
N/A
12/12/09: Verified with City Engineer - Engineering underway. Approximately 25% complete and should be completed in 2012.
 
6/21/2010: Verified by City - Design is underway. Anticipated to be completed in 2012
 
1/18/2011:  - SAME AS ABOVE
 
6/16/2011: Verified by City CIP Manager - The design contract for the project was awarded to KCI in January 2009.  The design is anticipated to be completed in 2012.
 
11/14/2011: Verified by City CIP Manager - SAME AS ABOVE
 
9/27/12: Verified by City CIP Manager - he design contract for the project was awarded to KCI in January 2009.  The design is anticipated to be completed in 2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07038
9/27/2012 9:09 AM
Tracy Homfeld
07-039McKinney
FM 1461
CR 127 (Custer Rd.)Lake Forest Drive
3.20
Engineering and Right-Of-Way
Design and right-of-way acquisition for four lanes of FM 1461 from Custer Road to Lake Forest Drive.
$1,400,000.00
$700,000.00
$700,000.00
10/1/2010
N/A
12/12/09: Verified by City Engineer
Engineering may be delayed due to no TxDOT funding for Construction.
 
6/21/2010: Project is being re-evaluated
 
1/18/2011: Project is being re-evaluated
 
6/14/2011: Verified by City CIP Manager - This project has been delayed due to decreased development activity and funding constraints.
 
11/14/2011: Verified by City CIP Manager - SAME AS ABOVE
 
9/27/2012: Verified by City CIP Manager - This project has been delayed due to decreased development activity.  County Bond funds may be reallocated to other City of McKinney projects as they are developed. 
http://maps.collincountytx.gov/bondrtr.html?pn=07039
9/27/2012 9:13 AM
Tracy Homfeld
Attachment07-040McKinney
Airport Drive
Industrial Blvd.US 380
1.80
Engineering and Construction
This project includes the design and construction of lanes 3 & 4 of Airport Drive from US 380 to Industrial Boulevard, a total distance of approximately 10,000 linear feet, and the construction of a traffic signal at the intersection of Airport Drive and Industrial Boulevard.  This project provides additional capacity to the area and is being used as an alternate route during the construction of the interchange at US 75 and US 380. 
24
$2,000,000.00
$497,772.00
$497,772.00
McKinney Economic Development
2/28/2009
COMPLETE
COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07040
7/8/2011 4:14 PM
Tracy Homfeld
07-041McKinney
SH 5 / McDonald
US 380Fm 543
1.90
Engineering and Right-Of-Way
This project includes the design and right-of-way acquisition for four lanes of SH 5 from US 380 to FM 543.
$2,000,000.00
$1,000,000.00
$1,000,000.00
10/1/2011
The design contract for this project is anticipated to begin in October 2011.
N/A
12/11/2009: Verified by City Engineer. Engineering to begin in Oct. 2011
 
6/21/2010: Verified by City - Due to funding constraints the schedule for this project is unknown.
 
1/18/2011: Same as above.
 
6/16/2011: Verified by City CIP Manager - This project has been delayed due to decreased development activity and funding constraints. 
 
11/14/2011: Verified by City CIP Manager - SAME AS ABOVE
 
9/27/2012: Verified by City CIP Manager - This project has been delayed due to decreased development activity.  County Bond funds may be reallocated to other City of McKinney projects as they are developed. 
 
Bond Funds in the amount of $500,000 were sold in 2008. Remaining funding scheduled in 2015.  
http://maps.collincountytx.gov/bondrtr.html?pn=07041
9/27/2012 9:18 AM
Tracy Homfeld
07-042McKinney
Virgina Pkwy.
Independence PkwyAero Country
0.50
Engineering and Construction
This project includes the design and construction of four lanes of Virginia Parkway from Independence Parkway to Aero Country Airport.
24
$2,000,000.00
$1,000,000.00
$1,000,000.00
12/11/2009: Status verified by City Engineer -
This project is driven by development north of Virgina Rd. therfore the project is delayed until the development is ready to proceed. 
 
6/21/2010: Verified by City - The design contract for this project is driven by the development of the tract located on the north side of Virginia.  The design has been completed and right of way acquisition for one of the key parcels is underway.  Due to funding constraints the schedule for construction of this project is not known.
 
1/18/2011: Same as above. No changes.
 
6/14/2011: Verified by City CIP Manager - SAME AS AVOVE
 
11/14/2011: Verified by City CIP Manager - SAME AS ABOVE
 
9/27/2012: Verified by City CIP Manager - This project is being developed by private resources.  County Bond funds may be reallocated to other City of McKinney projects as they are developed.
 
 
 
http://maps.collincountytx.gov/bondrtr.html?pn=07042
9/27/2012 9:19 AM
Tracy Homfeld
07-043McKinney
Custer Rd.
SH 121Stonebridge Dr.
3.10
Engineering and Construction46
$5,000,000.00
$2,500,000.00
$2,500,000.00
Project will be managed by the City of Frisco. Funding was sold in 2011 and is available.
http://maps.collincountytx.gov/bondrtr.html?pn=07043
11/14/2011 2:38 PM
Tracy Homfeld
Attachment07-044McKinney
Bloomdale Rd.
US 75Pecan Ridge
0.50
Engineering and Construction
This project includes the design and construction of 4 lanes of Bloomdale Road between US 75 and Shawnee Dr.  This project provides access to the area along Bloomdale Road east of US 75 including a recently completed elementary school.
04
$3,000,000.00
$1,500,000.00
$1,500,000.00
5/1/2008
2/1/2010
The design contract for the project was awarded to HDR in May 2008.  Plans are currently are complete.
6/30/2011
12/9/09: City Engineer confirmed. Should be ready for construction is April 2010.
 
6/21/2010: Verified by City -  The roadway was opened to traffic in April 2011 and clean-up items are currently underway. 
 
PROJECT COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07044
11/14/2011 2:39 PM
Tracy Homfeld
Attachment07-045McKinney
Lake Forest Dr.
Boyd High SchoolUS 380
1.00
Engineering and Construction
This project includes the design and construction of lanes 3 & 4 of Lake Forest Drive from Boyd HS to US 380 including a traffic signal at Lake Forest Drive and Raincrest (driveway to Boyd HS).  This project provides additional north-south capacity to the area including improved access to Boyd HS. The 2007
24
$5,200,000.00
$2,600,000.00
$2,600,000.00
The construction of the pavement and traffic signal are COMPLETE.
The 2008 Funding ($1,075,000) Interlocal Agreement has been approved. The City receieved the 2008 funds on 2-9-09.
 
PROJECT COMPLETE.
http://maps.collincountytx.gov/bondrtr.html?pn=07045
6/21/2010 11:00 AM
Tracy Homfeld
07-046McKinney
Lake Forest Dr.
US 380Wilmeth
1.10
Engineering and Construction
This project includes the design and construction of lanes four lanes of Lake Forest Drive from US 380 to Wilmeth.  This project provides additional capacity to the area north of US 380.
24
$5,800,000.00
$2,900,000.00
$2,900,000.00
11/30/2009
The design contract was awarded to Hayden Consulting.  The design is COMPLETE
1/31/2010
7/31/2011
Underway
12/11/2009: Verified by City Engineer:
Engineering COMPLETE. Construction contract awarded in Decemeber 2009 with a start date in January 2010.
 
6/21/2010: Verified by City - Construction contract awarded Dec 2009. Construction is underway and anticipated to be completed April 2011.
 
9/1/2010: Verified by City Project Manager - Project is 7 months into a 12 month construction contract. A little behind schedule but hope to be completed on time.
 
1/18/2011: Construction is on going and is 2-3 months behind. Should be completed late Spring 2011.
 
6/14/2011: Verified by City CIP Manager - The design contract was awarded to Hayden in August 2006.  The construction contract was awarded to Weir Bros. in January 2010.  The project was scheduled to be complete in February 2011; however, as of June 2011, the project is still incomplete and is estimated to be complete in July 2011.
 
11/14/2011: Verified by City CIP Manager - The design contract was awarded to Hayden in August 2006.  The construction contract was awarded to Weir Bros. in January 2010.  The project was scheduled to be complete in February 2011; however, as of November 2011, the project is still incomplete and is estimated to be complete in December 2011
 
9/27/2012: Verified by City CIP Manager - The design contract was awarded to Hayden in August 2006.  The construction contract was awarded to Weir Bros. in January 2010.  The project was scheduled to be complete in February 2011; however, the contractor defaulted on the contract.  The surety assumed responsibility for construction in May 2012.  Construction is anticipated to be complete in October 2012. 
 
1/23/2013: COMPLETE
 
http://maps.collincountytx.gov/bondrtr.html?pn=07046
4/16/2013 2:43 PM
Tracy Homfeld
07-047McKinney
Lake Forest Dr.
WilmethBloomdale
1.10
Engineering and Construction
This project includes the design and construction of lanes two and four lanes of Lake Forest Drive from Wilmeth to Bloomdale.  This project provides additional capacity along Lake Forest Drive north of US 380.
24
$3,600,000.00
$1,800,000.00
$1,800,000.00
5/1/2008
12/30/2009
The design contract for the project has been awarded to RLK Engineering in May 2008. Plans are at 90%
12/9/09: City Engineer confirmed Status update.
Engineering at 90% complete.
 
6/21/2010: Verified by City - The design contract for the project was awarded to RLK Engineering in May 2008.
 
1/18/2011: Engineering is at 90% Complete. No construction schedule determined.
 
6/14/2011: Verified by City CIP Manager - The engineering contract was awarded to RLK Engineering in May 2008.  Construction of this project has been delayed due to decreased development activity and funding constraints.   
 
11/14/2011: Verified by City CIP Manager - SAME AS ABOVE
 
9/27/2012: Verified by City CIP Manager - The engineering contract was awarded to RLK Engineering in May 2008.  Construction of this project has been delayed due to decreased development activity and funding constraints and is now anticipated to begin in 2014.   
 
1/23/2013: Same as above
http://maps.collincountytx.gov/bondrtr.html?pn=07047
4/16/2013 2:44 PM
Tracy Homfeld
07-048McKinney
Lake Forest Dr.
Bloomdale Rd.FM 1461 / CR 166
1.10
Engineering and Construction
This project includes the design and construction of two lanes of Lake Forest Drive from Bloomdale to FM 1461.  This project provides additional capacity along Lake Forest Drive north of US 380.
24
$4,500,000.00
$2,250,000.00
$2,250,000.00
12/11/2009: Status verified by City Engineer-
Project delayed until 2011.
 
6/21/2010: Due to funding constraints the schedule for this project is not known.
 
1/18/2011: The need for this project is being re-evaluated.
Bond funds programmed in 2011.
 
6/14/2011: Verified by City CIP Manager - This project has been delayed due to decreased development activity and funding constraints. 
 
11/14/2011: Verified by City CIP Manager - SAME AS ABOVE
 
9/27/2012: Verified by City CIP Manager - This project has been delayed due to decreased development activity.  County Bond funds may be reallocated to other City of McKinney projects as they are developed. 
 
1/23/2013: Same as above
http://maps.collincountytx.gov/bondrtr.html?pn=07048
4/16/2013 2:57 PM
Tracy Homfeld
Attachment07-049Melissa
Melissa Rd.
Denton St.SH 121
0.70
Engineering and Construction
Design of 4 lane divided/5 lane undivided roadway section from Denton Street to SH 121 along FM545 to SH121.  Construction/reconstruction of ~3,700 lf of existing two lane asphalt pavement roadway from SH5 to SH121 along Denton Street/FM 545. Proposed roadway will be a four-lane divided/five lane undivided concrete roadway section with a 37 foot median (where divided), curb and gutter and closed drainage system. Proposed project includes signalization upgrade at SH121, new signalization at SH5, signalization at Fannin Road/Melissa Road, a DART rail crossing, and partial right of way acquisition.
24
$4,560,000.00
$2,280,000.00
$2,280,000.00
3/4/2010: Consultant is preparing the Right of Way map and design schematic.
 
6/21/2010: Verified by City Engineer - Design schematics completed and ROW acquisition in progress.  City anticipates completing the design this fiscal year or early next
fiscal year.
 
1/14/2011: Verified by City Engineer - Design schematics completed and Right of Way aquisition is underway. Final Design to be completed FY 2011.
 
4/25/2011: Verified By City Engineer - Design is nearing a 60% completion stage. City anticipates completing the design by July of 2011.  Following completion of design, the City of Melissa will proceed with ROW acquisition. 
 
11/17/11: Verified By City Engineer - A portion of this roadway is on Melissa Hike and Bike trail, which required that schematics be revised to include bike lanes in the project.  Design schematics have been revised and the design is nearing a 90% completion stage.  We anticipate completing the design December of 2011.  Following completion of design, the City of Melissa will proceed with ROW acquisition.
 
1/23/2013: Project on hold
http://maps.collincountytx.gov/bondrtr.html?pn=07049
4/16/2013 2:58 PM
Tracy Homfeld
Attachment07-050Melissa
Throckmorton Rd.
US 75East of SH 5
1.75
Engineering and Construction
NEW ARTERIAL. Construct two lanes of ultimate four lane section of a new location roadway east of SH5. The project will include a bridge structure to cross Throckmorton Creek, intersection signalization at SH 5, a rail road crossing, right of way acquisition and utilities relocation and construction.
02
$7,330,000.00
$3,665,000.00
$3,665,000.00
6/1/2009
Phase I construction Completed.
Done in two phases:
PHASE I: East of SH 5 -
 
6/21/2010: Design complete. Advertised for Construction on January, 2009. Contractor Selected in April, 2009. Contract Awarded May, 2009. Notice to Proceed issued second quarter 2009. Construction began second quarter 2009 and is currently at 99% complete, pending only minor punchlist items.
 
1/14/2011: Verified by City Engineer-Phase I is COMPLETE
 
PHASE II: US 75 to SH 5 -
 
6/21/2010: Not active;
1/18/2011: Not Active;
4/25/2011: Not Active
11/17/20111: Not Active
http://maps.collincountytx.gov/bondrtr.html?pn=07050
11/17/2011 12:43 PM
Tracy Homfeld
07-051Melissa
Davis Rd.
US 75Fannin Rd.
0.50
Engineering and Construction
Design and reconstruction of an existing two lane flexbase roadway to a four-lane divided concrete roadway with curb and gutter and closed drainage system. Project will include signalization and right of way acquisition.
24
$2,300,000.00
$1,150,000.00
$1,150,000.00
Funding for this project programmed in 2013-2014.
 
11/17/11: No work completed on this project - project is not currently active
http://maps.collincountytx.gov/bondrtr.html?pn=07051
11/17/2011 12:45 PM
Tracy Homfeld
07-052Melissa
Fannin Rd.
Melissa Rd.SH 121
1.00
Engineering and Construction
Design and reconstruction of existing two-lane roadway to a four-lane divided roadway with curb and gutter and closed drainage system. Includes signalization at Melissa
Road.
24
$6,510,000.00
$3,255,000.00
$3,255,000.00
Funding for this project programmed in 2013-2014.
 
11/14/2011: No work completed on this project - project is not currently active.
http://maps.collincountytx.gov/bondrtr.html?pn=07052
11/17/2011 12:45 PM
Tracy Homfeld
07-053Murphy
Betsy Ln.
FM 2551McCreary Rd.
1.00
24
$2,407,000.00
$1,203,500.00
$1,203,500.00
2008 funding ($601,750) is in place. Remaining Funding ($601,750) is programmed in 2012.
 
2/15/2011 - No activity on this project
 
9/13/2011: Verified by City Manager - SAME AS ABOVE.
http://maps.collincountytx.gov/bondrtr.html?pn=07053
11/15/2011 2:01 PM
Tracy Homfeld
07-054Murphy
McCreary Rd.
McMillen Rd.CR 247 (McWhirter Rd.)
0.66
The Project shall consist of constructing a two-lane concrete roadway, a distance of approximately 2,600 feet.  The improvements shall also include construction of underground storm sewers as part of the road improvements.
24
$1,182,000.00
$591,000.00
$591,000.00
6/21/2010: Verified by City Consulting Engineer - City of Murphy has awarded an Engineering contract to Birkhoff, Hendricks and Carter, LLP.
 
2/15/2010: Verified by City Consulting Engineer - Project plans and specifications are 95% complete and lack only the City's final review and review changes they may require.
The City needs to secure ROW from two (2) parcels and easements from six (6) parcels. The City will be in a position to bid the project (pending funding from Collin County) after aquisition.
 
9/13/2011: Verified by City Manager - The City will begin construction on the McCreary Road project in January 2012. The construction bid documents will be prepared in October 2011.
 
4/18/2013: Verified by City Engineer - Construction of the project is near completion. The facility should be in full operation within a couple of weeks.  Punch list items to be completed.  
 
http://maps.collincountytx.gov/bondrtr.html?pn=07054
4/18/2013 1:53 PM
Tracy Homfeld
07-055Parker
McCreary Rd. (CR 245)
Parker Rd. (FM 2514)McWhirter Rd.
1.01
The proposed project is to construct a four lane
divided concrete roadway with enclosed storm
sewer system between McWhirter Road and Parker
Road. The length of the roadway is approximately
5320 feet.
24
$5,000,000.00
$2,500,000.00
$2,500,000.00
Design by CP&Y - Completed.
3/31/2010
Construction approximately 82% complete
6/21/2010: Verified by City - Construction is substantially complete.
 
1/14/2011: PROJECT COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07055
6/16/2011 5:00 PM
Tracy Homfeld
07-056Parker
Chaparral Drive
Springhill Estates DriveCottonwood Creek
0.50
24
$2,000,000.00
$1,000,000.00
$1,000,000.00
6/21/2010: Project has been delayed.
 
Funding Programmed in 2016.
http://maps.collincountytx.gov/bondrtr.html?pn=07056
6/16/2011 5:01 PM
Tracy Homfeld
07-057Plano
Major Thoroughfare Rehabilitation
1.99
Engineering and Construction
Major pavement replacement for Throughfare Projects.
 
2008 Funding Projects: 1)Plano Pkwy from DNT to Ohio, 2)Ohio Dr. from Old Shepperd to Plano Pkwy, 3) Legacy Dr from Custer to K Ave., 4) Legacy Dr. from Independence to Preston Rd. 5) Parker Rd from Independence to Coit, 6) Parker Rd. from Coit to Preston, 7) Pleasant Valley from Custer to Spring Crk, Park Blvd., 8) Park from Alma to Shiloh, 9) Park Blvd from Independence to Coit, 10) Plano Pkwy from Independence to Custer, 11) Jupiter from Summit to SH 190 
 
2009 Funding Projects: 1) Plano Prkwy from Commerce to K Ave., 2) Parker from Preston to DNT, 3) Legacy from Independence to Coit, 4) Preston Meadow from Parker to Quincy Lane, 5) Jupiter from Park to Summit, 6) Los Rios from Country Club to Park, 7) Ohio from Mapleshade to Sh 121, 8) Premier Dr. from Enterprise to Rusisseau Dr., 9) Legacy Dr. from Preston to SH 121.
 
2010 Funding Projects: 1) Custer Road from SH 190 to Spring Creek, 2) Spring Creek Parkway from Custer Road to Preston Road, 3) F Ave from Plano Pkwy to 4th, 4) Park from Ohio to Ventura, 5) Spring Cr from Pkwy K to Jupiter
 
2011 Funding Projects:   1) Coit - from Plano Parkway to Spring Creek Parkway 2)  Coit - from Spring Creek Parkway to SH 121
$15,000,000.00
$7,500,000.00
$7,500,000.00
2008 Funding Major Thorouoghfare Projects ($1,500,000): Complete.
 
2009 Projects ($1,360,000):  Under Construction.
7-6-2010: Almost Completed. Working on Plano Parkway. 1/21/2011: COMPLETE
 
2010 Projects ($1,500,000):  
 
7-6-2010: Under Design
 
1/21/2011: Verified by City Engineer - Construction on Custer Rd and Spring Creek Parkway underway
 
7/6/2011: Verified by City Engineer - Independence is on hold. Custer is under Construction. This project will end at Spring Creek Pkway. The Spring Creek pkway, F Ave, Park Blvd and other Spring Crk Pkway projects are complete.
 
1/9/2013: Verified by City Engineer - Projects have changed. Restated ILA to go to court soon. Funding remains same.
Independence is on hold so has been removed from restated ILA. Custer is under construction and project limits will end at Spring Creek. Spring Creek, F Ave, park and Spring Creek are complete.
 
2011 Projects:
1/9/2013 - Verified by City Engineer. Projects are complete. City will submit ILA for funding soon.
http://maps.collincountytx.gov/bondrtr.html?pn=07057
1/9/2013 11:48 AM
Tracy Homfeld
07-058Plano
Intersection Improvements
Major Intersection improvement for various Intersections.
 
2008 PROJECTS - 1) Plano Parkway @ Jupiter Road, 2) McDermott @ Robinson Rd., 3) Preston Rd. @ Legacy 4) Custer Rd. @ Park Bvd., Independence @ Parkhaven, Ohio @ SH 121, Spring Creek Pkwy @ Jupiter
 
2009 Projects - 1) Jupiter at Summitt and 10th Street and Spring Cr Pkwy at Jupiter 2) Plano Pkwy at Los Rios and Shiloh and Hedgcoxe and Coit
 
2010 Projects  - 1) Park Blvd corridor - Coit to Jupiter 2) Indep Pk. corridor - 15th to Parker 3) Parker Rd corridor - Coit, Independence and Alma 4) Spring Cr at Custer and Independence
 
2011 Projects - 1) Legacy Dr corridor- Custer to K  2) Preston Road corridor Parker to Headquarters 3) Jupiter at SH 190
 
2012 Projects - 1) Preston at Plano Pwky 2) Coit at Legacy
$22,750,000.00
$6,300,000.00
$10,500,000.00
$5,950,000.00
2008 FUNDING PROJECTS ($2,250,000)
COMPLETE
 
2009 Projects
 
7/8/2011: Verified by City Engineer
Project 1) Design is Complete.
Project 2) Under Design
 
1/9/2013: Verified by City Engineer
Project 1) Design is complete, ROW needed.
Project 2) Under Design
 
2010 Projects
 
7/8/2011: Verified by City Engineer
Engineering is ongoing on mutliple Intersection Projects.
 
1/9/2013: Verified by City Engineer - Consultants on 1, 2 & 4 have approved schematics and working on engineering plans 3.  working on schematic.
 
2011 Projects
 
7/8/2011: Verified by City Engineer
Schematic is complete on Legacy.  Design contract will be awarded on July 25th, 2011.  Working on Preston Road corridor.  Tennyson has been added to project.  Will be meeting with design consultant in July to start negotiations on Jupiter & SH 190.
 
1/9/2013: Verified by City Engineer - Schematic is complete on Legacy.  Design contract will be awarded on July 25th.  Working on Preston Road corridor.  Tennyson has been added to project.  Will be meeting with design consultant in July to start negotiations on Jupiter & SH 190
 
2012 Projects -
1/9/2013: Verified by City Engineer - Under TxDOT Design
http://maps.collincountytx.gov/bondrtr.html?pn=07058
1/9/2013 12:03 PM
Tracy Homfeld
07-059Plano
Toll Rd. / Chapel Hill Ramps
1.04
Engineering and Construction
Adding exit and entrance Ramps for Chapel Hill Blvd on DNT.
$10,000,000.00
$5,000,000.00
$5,000,000.00
Funds will be reallocated to another project at a later date.
http://maps.collincountytx.gov/bondrtr.html?pn=07059
2/10/2010 12:19 PM
BONANZA\gabriela
07-060Plano
Preston and SH 190
Adding additional left and right turn lanes to improve access to PGBT
$3,000,000.00
$0.00
$600,000.00
$2,400,000.00
5/1/2009
5/1/2011
7/8/2011: Verified by City Engineer
City to manage initial schematic which has been awarded.  TXDOT TO manage design and construction. Waiting on LPAFA. RTR Funds available. This funding will go towards local match.
 
12/5/2011: Verified by City Engineer - Schematic Design underway
 
1/9/2013: Verified by City Engineer - City to manage initial schematic which has been awarded.  TXDOT TO manage design and construction. Waiting on LPAFA. RTR Funds available. This funding will go towards local match.
http://maps.collincountytx.gov/bondrtr.html?pn=07060
1/9/2013 12:04 PM
Tracy Homfeld
07-061Plano
14 St.
K AvenueRidgewood Dr.
1.61
Engineering and Construction
Reconstructing existing 4 and 6 lane roadway.
$5,050,000.00
$1,550,000.00
$3,500,000.00
SH 121 Regional Toll Revenue Funding
10/1/2007
2/1/2010
Design by Teage, Nall and Perkins. Engineering is complete
3/1/2010
9/1/2011
Anticipate to start in March 2010 and will take 16 months to complete.
2/09/10: Verified by City Engineer - Construction to begin in March 2010. Plano city match will come from SH 121 Regional Toll Revenue Funds.
 
7/6/2010: Verified by City Engineer - Under Construction. To be completed Fall 2011.
 
1/14/2011: Verified by City Engineer - Construction is underway, paving completed on north side and working on south side from K east.
 
7/8/2011: Verified by City Engineer - Construction is underway. Majority of paving is complete.
 
12/5/11: PROJECT COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07061
12/5/2011 3:46 PM
Tracy Homfeld
07-062Plano
Communications Pkwy.
Spring Creek ParkwayTennyson
0.55
Engineering and Construction
Construction of 6 lane divided thoroughfare and widening of existing 4 lane section.
46
$2,500,000.00
$1,250,000.00
$1,250,000.00
10/1/2005
10/1/2010
COMPLETE
11/1/2009
6/30/2012
2/10/2010: Received 404 permits, design is 95% and should advertise for bids in August.
 
7/6/2010: Verified by City Engineer - Design is 95% Complete. Right of Way is being aquired. Should advertise for bids in September 2010.
 
1/14/2011: Verified by City Engineer - Plans being finalized. Will bid in February, 2011.
 
7/8/2011: Verified by City Engineer - Construction contract was awarded in June 2011.   The pre-construction meeting is on August 15th.  Estimated completion June 2012.
 
12/5/2011: Verified by City Engineer - Same as above
 
1/9/2013: Roadway opened to traffic in July and only final items remain to be completed by mid-February. COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07062
4/16/2013 3:25 PM
Tracy Homfeld
07-063Plano
15th St.
US 75G Avenue
0.24
Engineering and Construction
Reconstruction of existing roadway to complete a 4 lane divided thoroughfare.
64
$1,800,000.00
$0.00
$600,000.00
$1,200,000.00
2/1/2008
1/1/2011
Engineering by Nathan Maier. Consultant working on Schematic.
6/1/2011
6/1/2012
2/10/2010: TxDOT project. Plano will coordinate Engineering.
 
7/6/2010: Verified by City Engineer - Engineer is working on Schematic. Will submit to TxDOT soon.
 
1/14/2011: Verified by City Engineer - Engineer is working on Schematic.

7/08/2011: Verified by City Engineer - Project is on Hold. Changing funding from Federal to RTR.
 
12/5/2011: Verified by City Engineer - SAME AS ABOVE
 
1/9/2013: verified by City Engineer - SAME AS ABOVE
http://maps.collincountytx.gov/bondrtr.html?pn=07063
1/9/2013 12:09 PM
Tracy Homfeld
07-064Plano
Chaparral Bridge
@ Cottonwood Creek
Construction of the south 2 lanes for a bridge over Cottonwood Creek.
$1,000,000.00
$500,000.00
$500,000.00
1/1/2012
County Funding Scheduled for 2014-2015.
http://maps.collincountytx.gov/bondrtr.html?pn=07064
1/9/2013 12:11 PM
Tracy Homfeld
07-065Plano
Spring Creek Pkwy. (Shiloh Rd.)
Park Blvd.Parker Rd.
0.94
Engineering and Construction
Adding east 2 lanes to complete a 4 lane divided thoroughfare
$3,000,000.00
$1,500,000.00
$1,500,000.00
1/1/2010
County Funding scheduled for 2013-2014
http://maps.collincountytx.gov/bondrtr.html?pn=07065
1/9/2013 12:13 PM
Tracy Homfeld
07-066Plano
Shiloh Rd.
14th StreetPark Blvd.
1.15
Engineering and Construction
Adding east 2 lanes to complete a 4 lane Divided Thoroughfare
$2,800,000.00
$1,400,000.00
$1,400,000.00
1/1/2010
County Funding Scheduled for 2013-2014.
http://maps.collincountytx.gov/bondrtr.html?pn=07066
1/9/2013 12:13 PM
Tracy Homfeld
07-067Plano
Los Rios Blvd.
South of Plano ParkwayParker Road
3.88
Engineering and Construction
Widening exisiting 4 lane to 6 lane divided Thoroughfare.
 
Phase I - South of Plano Parkway to 14th Street ($1,000,000)
 
Phase II - 14th Street to park ($1,000,000):
$4,000,000.00
$2,000,000.00
$2,000,000.00
Will be done in Phases:
 
Phase 1: South of Plano Parkway to 14th Street ($1,000,000) Scheduled for 2014-2015
 
Phase 2: 14th Street to park ($1,000,000): City Thoroughfare plan revised to reflect a 4 lane divided road which currently exists. This funding will be reallocated to another project at a later date.
http://maps.collincountytx.gov/bondrtr.html?pn=07067
1/9/2013 12:17 PM
Tracy Homfeld
07-068Plano
Park Blvd.
ShilohEast City limits
1.04
Engineering and Construction
Widening exisiting 4 lane to 6 lane Divided Thoroughfare
$1,900,000.00
$950,000.00
$950,000.00
Funding scheduled for 2016.
http://maps.collincountytx.gov/bondrtr.html?pn=07068
7/6/2010 12:21 PM
Tracy Homfeld
07-069Plano
Mapleshade Dr.
Silverglen Rd.SH 190
0.47
Engineering and Construction
Extension of 4 lane divided roadway to connect to SH 190.
$750,000.00
$375,000.00
$375,000.00
1/1/2011
1/1/2012
Scheduled in 2012-2013
http://maps.collincountytx.gov/bondrtr.html?pn=07069
1/9/2013 12:21 PM
Tracy Homfeld
07-070Plano
Los Rios Blvd.
South of Plano Parkway14 st
1.61
Engineering and Construction
Widening existing 4 to 6 lanes
$2,000,000.00
$700,000.00
$1,000,000.00
$300,000.00
Scheduled for 2012-2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07070
1/9/2013 12:22 PM
Tracy Homfeld
07-071Plano
Ridgeview Dr.
SH 121Coit Rd.
0.93
Engineering and Construction
Extension and widening of existing 2 lane to divided 4 lane Thoroughfare.
$2,000,000.00
$1,000,000.00
$1,000,000.00
Scheduled for 2014-2015.
http://maps.collincountytx.gov/bondrtr.html?pn=07071
1/9/2013 12:23 PM
Tracy Homfeld
07-072Plano
International Pkwy.
Plano ParkwayMidway Rd.
0.54
Engineering and Construction
Widening 4 lane to 6 lane Divided Thoroughfare.
$800,000.00
$400,000.00
$400,000.00
Scheduled for 2014-2015.
http://maps.collincountytx.gov/bondrtr.html?pn=07072
1/9/2013 12:23 PM
Tracy Homfeld
07-073Plano
Brand Rd.
South of FM 544
0.77
Engineering and Construction
Widening 4 lane to 6 lane divided Thoroughfare.
$800,000.00
$400,000.00
$400,000.00
Scheduled for 2014-2015.
http://maps.collincountytx.gov/bondrtr.html?pn=07073
1/9/2013 12:24 PM
Tracy Homfeld
07-074Plano
McDermott Rd.
Coit RdOhio Rd
1.52
Engineering and Construction
Widening existing 4 lanes to a 6 lane divided Thoroughfare.
$4,000,000.00
$0.00
$400,000.00
$3,600,000.00
1/1/2007
Design is completed.
4/1/2010
10/31/2010
Under Construction
2/09/2010: Verified by City Engineer - Construction will begin in April 2010and be completed in about 12 months.
 
7/6/2010: Verified by City Engineer. Under Construction. To be complete Fall 2010.
 
2/15/2011: Project is COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07074
7/8/2011 4:11 PM
Tracy Homfeld
07-075Plano
Parker Rd. Interchange
@ US 75
Intersection Improvement. Single Point Urban Interchange (SPUI)
$20,250,000.00
$0.00
$4,000,000.00
$16,250,000.00
11/30/2010
Funds will be reallocated to future project.
 
Project is fully funded by RTR funds. TxDOT is constructing presently and is scheduled to be completed Nov. 2010.
 
7/8/2011: TxDOT Construction is COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07075
11/18/2011 1:32 PM
Tracy Homfeld
07-076Plano
Ridgeview Dr.
Coit Rd.Independence Parkway
1.14
Engineering and Construction
Widening existing 4 lanes to a 6 lane divided Thoroughfare.
$2,000,000.00
$1,000,000.00
$1,000,000.00
$1,000,000.00
8/1/2007
3/1/2009
Design
7/1/2009
7/1/2010
Construction substantially Complete
7/6/2010: Verified by City Engineer. Construction COMPLETE. All lanes are open.
http://maps.collincountytx.gov/bondrtr.html?pn=07076
7/8/2011 4:12 PM
Tracy Homfeld
07-077Princeton
CR 407 (Monte Carlo Blvd.)
US 380FM 75
2.27
Engineering and Construction
The Project shall consist preparing Engineering plans and specifications and construction of a four-lane divided concrete roadway, a distance of approximately 2.25 miles.  The improvements shall also include construction of underground storm sewers as part of the road improvements.
 
The project will be constructed in phases. The southern half (eastbound lanes) of the roadway from US380 on the west to Tickey Creek on the East (Just west of FM 75) will be constructed first. It will be two lane concrete curb & gutter.  Included in the project is underground storm drainage and culverts for cross drainage for the entire length.  The Northern lanes (westbound) of pavement from US 380 to approximately 1000’ North of US 380 will be constructed concurrently with the remainder of the northern lanes to be done in phase II. A 20” waterline is included in the areas where the full road is being constructed. 
 
22-4
$15,542,000.00
$7,771,000.00
$7,771,000.00
COMPLETE
1/2/2010
4/1/2011
On going

6/21/2010: Under Construction

1/5/2011: Verified by Project Engineer - Scope was added to the project and the completion date has been changed to March 2011.  They’ve completed two lanes from US 380 to the Ticky Creek bridge.  Almost all drainage has been completed.  They are now working on the additional two lanes from US 380 to approximately to Palermo as well as the Waterline.  They are expected to complete in late March or early April 2011.

11/18/2011: Phase I (2 of the 4 lanes from US 380 to FM 75) has been completed. Phase II Interlocal Agreement with the county is under review.

1/25/2013: Verified by City Engineering Co. - Phase II etimated Construction complete March 2013. Limits Palermo Ct to Tickey Creek Bridge.

http://maps.collincountytx.gov/bondrtr.html?pn=07077
1/25/2013 11:06 AM
Tracy Homfeld
Attachment07-078Prosper
Prosper Trail
DNTPreston Rd
1.98
Engineering and Construction
Prepare Engineering Plans, aquire Right of Way, Utility relocation and Construction of a 4-lane divided concrete curb and gutter roadway from DNT to BNSF Railroad and from Coleman St (Business 289) to Preston Road (SH 289). Construction will also include underground storm sewer.  
24
$4,435,425.00
$2,217,713.00
$2,217,713.00
6/30/2009
10/1/2009
5/31/2011
COMPLETE
6/21/2010: Verified by Town - The utilities are 95% complete. The contractor has paved the west bound lanes between Preston and Coleman and is currently working on backfill and sidewalk prior to opening to traffic. The proposed area between Coleman and the Dallas North Tollway has been limed and paving of this area should commence next week.  Construction from Sep. 2009 - May 2011
 
1-7-2011: Verified by City CIP Manger  - Construction is 97% complete. Opened to traffic around Thanksgiving 2010. Remaining cosmetic itens to be completed within 30 days. COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07078
6/17/2011 1:34 PM
Tracy Homfeld
Attachment07-079Prosper
First Street
Preston RdCoit Rd
1.25
Engineering and Construction
Widening the Existing 2-lane asphalt roadway to a 4-lane divided roadway with concrete curb and gutter and underground drianage. Turn lanes to facilitate future traffic demands are included in this project.
24
$3,033,344.00
$1,516,672.00
$1,516,672.00
10/31/2009
Design Complete
Design Completed in October 2009.
 
6/21/2010: Verified by Town - Will bid and award construction contract June 2010. Construction anticipated to start shorty after.
 
1/7/2011: Verified by Town CIP Manager - Utility relocation underway. Construction to start shortly.
 
6/17/2011: Verified by Town CIP Manaher - The franchise utilities are continuing to work on clearing their facilities. 
 
11/17/2011: The City has re-awarded the contract  to Tiseo Paving Co. Expectations are to hold a Pre-Con in early December and start dirt work shortly thereafter.
Utilities work should conclude the first quarter of 2012. The project is expected to be completed in the summer of 2013.
 
1/25/2013 - Verified by City Eng. Dept - Completed 80% of the storm sewer. Paving has begun at the Coit Road intersection and a portion of the east bound lanes. Expected completion is summer 2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07079
1/25/2013 11:34 AM
Tracy Homfeld
Attachment07-080Prosper
Coit Rd.
First St.US 380
1.00
Engineering and Construction
Widening the Existing 2-lane asphalt roadway to a 4-lane divided roadway with concrete curb and gutter and underground drianage. Turn lanes to facilitate future traffic demands are included in this project.
24
$2,285,806.00
$1,142,903.00
$1,142,903.00
10/30/2009
Design Completed
6/6/2011
Design Completed in October 2009.
 
6/21/2010: Verified by Town - Construction bid to be awarded in June 2010 and construction to start shortly thereafter.
 
1/7/2011: Verified by Town CIP Manager - Utility relocation underway. Construction to start shortly.
 
6/17/2011: Verified by Town CIP Manager - The contractor began working June 6th on clearing and balancing the grades ahead of the storm sewer work.
 
11/17/2011: The City has re-awarded the contract  to Tiseo Paving Co. Expectations are to hold a Pre-Con in early December and start dirt work shortly thereafter.
Utilities work should conclude the first quarter of 2012. The project is expected to be completed in the summer of 2013.
 
1/25/2013: Verified by City Eng. Dept. - The paving of Coit Road is approximately 70% complete. City has switched traffic to the new concrete, south of Lewis Canyon, and has begun excavating for the medians and left turn lanes. Anticipate construction to be substantially complete spring 2013.
 
http://maps.collincountytx.gov/bondrtr.html?pn=07080
1/25/2013 11:36 AM
Tracy Homfeld
07-081Richardson
Alma Rd.
@ Renner Rd
Intersection Improvement
$115,000.00
$57,500.00
$57,500.00
City has requested that 07 bond funds be reallocated to fund 03-122 - Performance Drive. 2007 Bond Projects will be built utilizing 100% City Funding.
http://maps.collincountytx.gov/bondrtr.html?pn=07081
2/10/2010 12:19 PM
BONANZA\gabriela
07-082Richardson
Jupiter Rd.
@ Renner Rd
Intersection Improvement
$295,000.00
$147,500.00
$147,500.00
City has requested that 07 bond funds be reallocated to fund 03-122 - Performance Drive. 2007 Bond Projects will be built utilizing 100% City Funding.
http://maps.collincountytx.gov/bondrtr.html?pn=07082
2/10/2010 12:19 PM
BONANZA\gabriela
07-083Richardson
Jupiter Rd.
@ SH 190
Intersection Improvement
$185,000.00
$92,500.00
$92,500.00
City has requested that 07 bond funds be reallocated to fund 03-122 - Performance Drive. 2007 Bond Projects will be built utilizing 100% City Funding.
http://maps.collincountytx.gov/bondrtr.html?pn=07083
2/10/2010 12:19 PM
BONANZA\gabriela
07-084Richardson
SH 190
@ Renner Rd
Intersection Improvement
$145,000.00
$72,500.00
$72,500.00
City has requested that 07 bond funds be reallocated to fund 03-122 - Performance Drive. 2007 Bond Projects will be built utilizing 100% City Funding.
http://maps.collincountytx.gov/bondrtr.html?pn=07084
2/10/2010 12:19 PM
BONANZA\gabriela
07-085Richardson
Performance Dr.
SH 190Renner Rd.
0.28
Engineering Only04
$254,000.00
$127,000.00
$127,000.00
City has requested that 07 bond funds be reallocated to fund 03-122 - Performance Drive. 2007 Bond Projects will be built utilizing 100% City Funding.
http://maps.collincountytx.gov/bondrtr.html?pn=07085
2/10/2010 12:19 PM
BONANZA\gabriela
07-086Richardson
Renner Rd.
Northstar Dr.Murphy Rd.
1.80
Engineering Only46
$900,000.00
$450,000.00
$450,000.00
City has requested that 07 bond funds be reallocated to fund 03-122 - Performance Drive. 2007 Bond Projects will be built utilizing 100% City Funding.
http://maps.collincountytx.gov/bondrtr.html?pn=07086
2/10/2010 12:19 PM
BONANZA\gabriela
07-087Sachse
Ranch Rd.
W. of Woodbridge Unit 14Hwy 78
0.61
Engineering and Construction
The Ranch Road project constructs the eastbound 2-lanes of a 4-lane divided roadway beginning at State Highway 78 and extending west approximately 3,200 feet.
$960,000.00
$480,000.00
$480,000.00
12/14/2009: Verified by City Engineer
Project anticipated beginning the first quarter of 2012.
 
6/15/2010:
Verified by City Engineer
Project engineering may begin in FY 2011 with anticipated Construction in 2012-2013 depending on funding availability.
 
1/14/2011: Verified by City Engineer - Project scheduled to begin 2012-2013.
 
9/12/2011: Verified by City Engineer - Project scheduled to begin FY 2012-2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07087
11/18/2011 1:21 PM
Tracy Homfeld
Attachment07-088Sachse
DeWitt Rd.
Ingram Rd.Ranch Rd.
0.48
Engineering and Construction
It adds 2-lanes (southbound) to complete the 4-lane divided roadway between Ingram Rd. to Ranch Road.  The existing pavement will remain and will function at the northbound lanes.
$720,000.00
$360,000.00
$360,000.00
COMPLETE
8/3/2009
8/31/2010
On Going
1/15/2010: Verified by City Engineer
Project is under construction.
 
6/15/2010: Verified by City Engineer
Project Under Construction and should be completed by the end of August.
 
1/18/2011: PROJECT COMPLETE.
http://maps.collincountytx.gov/bondrtr.html?pn=07088
6/17/2011 12:52 PM
Tracy Homfeld
07-089Sachse
Maxwell Creek Rd.
Ranch RdNorth City Limits
0.93
Engineering and Construction
The Maxwell Creek Road project expands an existing 2-lane roadway to a 4-lane divided roadway from Ranch Road to the northern City of Sachse limit.
$1,730,000.00
$865,000.00
$865,000.00
12/14/09: Verified by City Engineer
The Design will start in first quarter 2011.
 
6/15/2010: Verified by City Engineer
Project engineering may begin in FY 2011 with anticipated Construction in 2012-2013 depending on funding availability.
 
1/14/2011: Design scheduled to begin mid Fiscal year 2011.
 
9/12/2011: Design anticipated to begin Mid FY 2012.
http://maps.collincountytx.gov/bondrtr.html?pn=07089
11/18/2011 1:19 PM
Tracy Homfeld
07-090Wylie
Brown St.
FM 1378Ballard Ave
1.80
Engineering and Construction
The Project shall consist of Engineering and constructing a 4-lane divided concrete roadway, a distance of approximately 8,900 feet.  The improvements shall also include construction of underground storm sewers as part of the road improvements.
 
West Brown Street: FM 1378 to Ballard
East Brown Street: Sh 78 to Stone Rd.
24
$12,270,000.00
$7,816,250.00
$4,453,750.00
6/21/2010: Verified by City Engineer - City is acquiring right of way on Brown Street West.  The engineering plans are at 85% and have approved an agreement with  NTMWD to relocate a 14” water line and their 60” water line crossing.  City bond funds have been issued and as soon as right of way is acquired and utilities are moved we will be ready to advertise the project.  Right of way is scheduled to be completed in September 2010 and the construction should start in 2011. 
 
1/11/2011: Verified by City Engineer - Design is approximately 90% complete.  City is purchasing right of way and are about half way done.  NTMWD is relocating their 14” and a portion of 60” water line in preparation for the project.  The City expects to notify utility companies to move their facilities in the next couple of months. 
 
4/26/2011 - Verified by City Engineer. City is almost complete with the Right of Way aquisition process. Utility companies will be put on notice next month.
 
11/4/2011: Verified by City Engineer - The City will advertise the Brown Street West project in December and open bids in January 2012. Construction to start shortly thereafter.
 
1/23/2013: Verified by City Engineer - East and West Brown street are under construction.
http://maps.collincountytx.gov/bondrtr.html?pn=07090
1/23/2013 10:40 AM
Tracy Homfeld
07-091Wylie
McMillen Rd. (Park Blvd.)
E. of McCrearyFM 1378
1.09
Engineering and Construction
The project includes preparing Engineering plans and specifications and construction of a 4-lane divided concrete roadway. The improvements shall also include construction of underground storm sewers as part of the road improvements.
$8,298,750.00
$4,149,375.00
$4,149,375.00
85% Complete
2/10/2010: Wylie City Council has approved the alignment and Binkley & Barfield will be submitting a 30% set of Dec 2009.
 
6/21/2010: Verified by City Engineer - Construction plans are approximately 60% complete.
 
1/23/2013: Verified by City Engineer - Design is 95% complete.

1/11/2011: Verified by City Engineer - Plans are 65% complete and the city is meeting with property owners to discuss the needed right of way.
 
4/26/2011: Verified by City Engineer - Plans are 85% complete. Right of Way needs are being finalized.
 
11/18/2011: Verified by city engineer - Same as above
 
http://maps.collincountytx.gov/bondrtr.html?pn=07091
1/23/2013 10:41 AM
Tracy Homfeld
Attachment07-092Wylie
Stone Rd.
Akin lnCounty Line Rd
1.99
Engineering and Construction
Project includes land acquisition, engineering, and constructionof a 4-lane divided concrete roadway. The improvements shall also include construction of underground storm sewers as part of the road improvements.
$10,042,500.00
$5,021,250.00
$5,021,250.00
90%
2/10/2010: Wylie City Council approved the alignment at the Stone/WA Allen intersection.  A 60% plan submittal was done in December.  Construction contract to be bid Summer of 2010.
 
6/21/2010: Verified by City Engineer - Consultant is revising plans per City comments on the 65% submittal. Anticipate starting right of way acquisition in July 2010 which should take 2-3 months to complete.  This project should be under construction in FY11.
 
1/11/2011: Verified by City Engineer - Plans are 65% complete and the right of way documents have been sent to the ROW agent for a proposal.  City expects that this project will be bid this year.

4/26/2011: Verified by City Engineer - Engineering at 90% Complete. Right of Way acquisition has begun.
 
11/18/2011: Verified by City Engineer - Same as above
 
1/23/2013: Verified by City Engineer - The city will advertise for construction Spring 2013
http://maps.collincountytx.gov/bondrtr.html?pn=07092
1/23/2013 10:42 AM
Tracy Homfeld
07-093Collin County
Lake Lavon Bridge - LOCATION STUDY
8.66
Engineering Only
Bond Funds are for a location study only. NO CONSTRUCTION FUNDING HAS BEEN IDENTIFIED.
$366,987.00
$366,987.00
HNTB has been selected as the Engineering firm. Location Study in early stages. The first public meeting was held in Wylie, TX on October 7, 2009. A copy of the presentation and agenda are available at: http://www.co.collin.tx.us/engineering/index.jsp
 
6/21/2010: Second Public meeting was held on May 19, 2010 in Wylie. Meeting presentation and agenda can be found on the link above. All comments received by June 2nd will be addressed in the final report to be completed this summer.
 
1/19/2011: The Final report has been completed and presented to Commissioners Court. The Court voted to not move forward and to remove the designation from the county thoroughfare map. EFFORT COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07093
7/8/2011 4:17 PM
Tracy Homfeld
07-094Collin County
Outer Loop: SEGMENT 1
US 75SH 121
4.89
Engineering and Construction
Engineer and Construct 2 lane service road of the future Outer Loop From US 75 to SH 121
02
$5,025,000.00
$12,000,000.00
Regional Toll Revenue Funding
12/31/2010
COMPLETE
1/26/2011
8/4/2012
Construction contract has been awarded and is ongoing.
6/21/2010: Engineering is complete. Working on the Advanced Funding Agreement with TxDOT to obtain the Regional Toll Revenue funds. Funds should be in place within 3 months. Should be ready to bid construction of 2 lane service road by late summer.
 
1/19/2011: Construction Contract has been awarded to LH Lacy. Contractor should be mobilizing very soon and project should be completed by Summer 2012.
 
1/26/2011: Notice to proceed was issued today. Contruction end date is Aug. 4, 2012.
 
4/30/2011: Several Box culverts have been installed. Clearing and grading is ongoing.
 
10/31/2011: Construction is ongoing. Continued work on bridge and road surface. Continued Right of Way clearing and fence installation.
 
1/23/2013: The sections from US 75 to SH 5 and from SH 121 west to just before the railroad are completed. The Railroad will be constructing the new crossing this spring to finalize the project.
http://maps.collincountytx.gov/bondrtr.html?pn=07094
1/23/2013 10:45 AM
Tracy Homfeld
Attachment07-095Collin County
Outer Loop: SEGMENT 3
Dallas North TollwaySH 289
1.80
Engineering and Construction
Engineer and Construct a 2 lane service rd for the Future Outer Loop from the DNT to SH 289
$4,962,000.00
Alignment update underway
6/21/2010: No bond funds have been sold for this project. The county is using current funding to refine the alignment. We are also preparing an RFQ/RFP for construction of Seg. 3. Bond funds will be sold at a later date as needed. CH2MHill is the consulting Engineer.
 
1/19/2011: We have completed our RFQ/RFP process for Public Private Partnership interest. Alignment refinement is on going by CH2MHill. No construction schedule is identified.
 
6/17/2011: A public hearing was held in May to determine the technically preferred alignment for Seg 3. The CCTRA will vote on it in August.
 
11/14/11: The board has asked that the consultants look at another alignment option. Engineering is negotiating with the consultant to update their scope of work.
 
1/23/2013: The refined alignment was approved last year. We are negotiating scope with the engineer to prepare a schematic for a two lane service road from DNT to SH 289.
http://maps.collincountytx.gov/bondrtr.html?pn=07095
1/23/2013 10:46 AM
Tracy Homfeld
07-096Collin County
CR 408
Road Bend East of Bomars BranchFM 75
2.00
Right-of-Way Only
The 2007 Bond program is funding for Right of Way aquisition only. The Construction will be done by Public Works.
$770,000.00
$770,000.00
The 2007 Bond funding is for Right Of way Aquisition only.  The Construction will be done by Public Works.
 
2/22/2010: Bohannan Houston has completed surveying and is now preparing Right of Way Exhibits and should be completed by the end of February. Once receieved we will proceed with the appraisal process.
 
6/21/2010: Verified by Special Projects Manager - The ROW exhibits and descriptions are complete. Right of Way Acquisition underway.
 
1/18/2011: ROW has been obtained for 16 of the 34 parcels.
 
6/6/2011: Verified by Special Projects Manager - ROW has been obtained for 30 of 34 parcels.
 
11/1/2011: Verified by Special Projects manager - ROW has been obtained for 32 of 34 parcels.
 
1/23/2013: Right of Way has been completed.
 
http://maps.collincountytx.gov/bondrtr.html?pn=07096
1/23/2013 10:46 AM
Tracy Homfeld
07-097Collin County
CR 618
CR 665 EastCounty Line
1.80
Right-of-Way Only
The 2007 Bond funding is for Right-of-Way aquisition only. Construction will be done by Public Works.
$407,000.00
$407,000.00
The 2007 Bond funding is for Right-of-Way acquisition only. Construction will be done by Public Works.
 
2/22/2010: Bohannan Houston has completed the field work and Right of Way exhibits. They have been submitted to us and we had several changes. Once the changes have been made we will proceed with the appraisal process.
 
6/21/2010: Verified by Special Projects Manager - The ROW exhibits and descriptions are complete. Awaiting a cost proposal for the appraisals.
 
1/18/2011: Verified By Special Projects Manager - To date, ROW has been obtained for 7 of the 22 parcels.
 
6/6/2011: Verified By Special Projects Manager - To date, ROW has been obtained for 19 of the 22 parcels.
 
11/1/2011: Verified by Special Projects Manager - All Right of Way has been obtained and project is being turned over to Public Works to pave. - COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07097
11/18/2011 4:05 PM
Tracy Homfeld
Attachment07-098Collin County
CR 819 (Ballard St.)
Alanis StreetCounty Line
1.20
Engineering and Construction
Reconstruction of Existing 2-lane asphalt roadway to a 4-lane divided concrete roadway with closed conduit storm drain system, illumination and irrigation. Will involve Utility relocation. This is a Collin County bond project being managed by the City of Wylie.
$5,400,000.00
$5,400,000.00
4/1/2009
Engineering contract awarded to RLK. 90% Complete.
2/10/2010: This project is being managed through the City of Wylie. Engineering is underway.
 
7/6/2010: Verified by City Engineer - The construction plans are approximately 30% complete.  Construction to begin in 2012 depending on County funding availability.
 
1/11/2011: Verified by City Engineer - Design plans are at 30%.
 
9/19/2011: Verified by City Engineer - Plans are approximately 60% complete.  Construction bidding delayed until late 2012 due to Right of way acquisition and utility relocations. 
 
12/11/2012 - Verified by City Engineer - Plans are approximately 90%. Right of Way acquisition should begin shortly.
 
1/23/2013 - Verified by City Engineer - Plans are 90% complete. Construction to start in 2013.
http://maps.collincountytx.gov/bondrtr.html?pn=07098
1/23/2013 10:48 AM
Tracy Homfeld
07-099Collin County
Park Blvd.
FM 2514 (Parker Rd.)Spring Creek Parkway
1.20
Right-of-Way Only
The 2007 Bond program is funding for Right of Way aquisition only. (Approx. 45 Parcels)
$1,130,000.00
$1,130,000.00
Funding will be made available in 2012.
http://maps.collincountytx.gov/bondrtr.html?pn=07099
6/21/2010 2:30 PM
Tracy Homfeld
07-100Collin County
CR 170
FM 2478Honey Creek
1.60
Right-of-Way Only
The 2007 Bond program is funding for Right of Way aquisition only.
$616,000.00
$616,000.00
6/21/2010: The surveyor (Bohanan-Huston) has begun the field work on this project.
 
1/04/2011: Verified by Special Projects Manager - The exhibits and property descriptions are complete. Review notes have been submitted to the surveyor. 
 
6/6/2011: Verified by Special Projects Manager - Appraisals are being prepared.
 
11/1/2011: Verified by Special Projects Manager - Offer letters were mailed September 1st and 7 parcels have been obtained to date.
 
COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07100
4/16/2013 3:40 PM
Tracy Homfeld
07-101Collin County
CR 424
Sheffield FarmsCR 509
1.00
Construction Only
Public Works will do the construction.
$1,320,000.00
$1,320,000.00
Funding has been reallocated to County rural roads and drainage with cost over runs. 
http://maps.collincountytx.gov/bondrtr.html?pn=07101
2/10/2010 12:19 PM
BONANZA\gabriela
07-102Collin County
CR 408 @ Bomars Branch
New Hope City LimitsRoad Bend
0.50
Engineering and Construction
Construction of a 24'x12' and a 24'x8' concrete box culvert to include reconstruction of approximately 1,100 LF of existing 18-20 ft. wide asphalt roadway to a 24 ft. wide asphalt roadway.
$660,000.00
$660,000.00
9/1/2008
Binkley and Barfield are currently doing final design. Plans are complete
8/1/2011
2/28/2012
Construction Contract award by the end of June 2011.

Plans are at 90%. Final Right of Way exhibits have been delivered to the county. Land Owner Bill of Rights letters will go out this week followed by offer letters approximately a week later.

7/6/2010: 2 of the 3 parcels have been acquired. Should be completed with Right of Way aquisition late summer 2010.

1/04/2011: 2 of the three parcels have been acquired. Once ROW aquisition is complete we will bid the construction contract.

6/17/2011: All ROW has been obtained. Construction contract will be awarded on 6-27-2011. Construction to start late July or early August 2011. Water line and phone lines have been relocated.

11/15/2011 - Construction is underway. West structure is going in first and the top slab has been poured.

12/11/2012 - COMPLETE

http://maps.collincountytx.gov/bondrtr.html?pn=07102
12/11/2012 3:15 PM
Tracy Homfeld
07-103Collin County
CR 618 @ Cedar Creek
Engineering and Construction
Replacing 2 existing metal culverts with concrete box culverts. The new structures will require less maintenance in the future.  
$363,000.00
$363,000.00
10/1/2008
7/1/2009
Dannenbaum is complete.
COMPLETE
2/22/2010: Dannenbaum has completed the plans. We will advertise for bids in February 2010.
 
6/21/2010: Construction is underway. Anticipate completion in late August Early Sept.
 
1/4/2011: This project is essentially COMPLETE and the roadway has been open to traffic since October. 
 
6/06/2011: Work in the Creek is ongoing.
 
11/1/2011: Verified by Special Projects Manager - Structure is complete but work in the creek is ongoing.
 
4/16/13: Same as above
http://maps.collincountytx.gov/bondrtr.html?pn=07103
4/16/2013 3:51 PM
Tracy Homfeld
07-104Collin County
CR 638 @ Sabine Creek
Engineering and Construction
Replacing 2 existing metal culverts with a 50 foot bridge.
$412,500.00
$412,500.00
Gojer and Associates - Plans are complete.
3/31/2010
Complete
2/22/2010: Gojer and Associates are finalizing plans. The Right of Way has been acquired. Utility contractors are being contacted in preparation for construction. Construction to begin in March 2010.
 
6/21/2010: Design Complete. Project has been awarded to JMI, Inc. Pre bid meeting to be held shortly with constructed to follow thereafter.
 
1/04/2011: PROJECT COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07104
6/17/2011 9:32 AM
Tracy Homfeld
07-105Collin County
SH 121
SH 5Fannin County Line
Engineering Only
COUNTY DISCRETIONARY PROJECT: Preliminary Engineering and Environmental Documument
$420,010.00
$420,010.00
Preliminary Engineering to Environmental Clearance - On going by LAN
7/6/2010: County funded preliminary Engineering for TxDOT to keep project moving. Engineering on going by LAN.
 
1/26/2011: Verified by Project Manager at LAN - The Env. Document is under review by TxDOT. The Public Hearing hopefully will be scheduled in the next couple of months. After the hearing, the Env. document will go through a summary analysis. Once accepted, this bond project will be completed. Final Engineering will need to be completed after that and then
construction dollars have been allocated for SH 121 from SH 5 to SH 455 only using Regional Toll Revenue Dollars.
 
6/17/2011: Waiting on Sufficient for Processing Status from TxDOT. Anticipate a Public Hearing to be held this fall 2011.
 
11/18/2011: Public Hearing was held on November 1, 2011.  Environmental clearance is expected by the end of Dec 2011. Final Engineering is funded by RTR. Construction from SH 5 to FM 455 final engineering is being done by TxDOT. Construction for the portion from SH 5 to FM 455 is being funded with RTR dollars and the let date is Nov 2012.
11/18/2011 4:11 PM
Tracy Homfeld
07-106Collin County
CR 127 @ How Branch
Engineering and Construction
Replacing Metal Culvert with a Concrete Box Culvert.
$341,000.00
$341,000.00
9/1/2008
Binkley and Barfield is the consulting engineer. COMPLETE
Engineering is COMPLETE.
 
2/22/2010: Starting the Right of Way aquisition process.
 
6/21/2010: Plans at 90% complete. Right of Way acquisition underway and should be completed in June 2010.
 
1/04/2011: The plans and specs are complete.  We plan to advertise this project for construction in February 2011.
 
6/6/2011: This project was awarded to Jeske Construction and construction began the week of 4/22. The box culvert floor has been poured and the walls are scheduled to be poured on 6/3/2011.
 
11/1/2011: Verified by Special Projects Manager - Project is COMPLETE and roadway is opened to traffic
 
http://maps.collincountytx.gov/bondrtr.html?pn=07106
11/15/2011 9:40 AM
Tracy Homfeld
07-107Collin County
CR 617 @ Branch of Hickory Creek
Engineering and Construction
Replacing the existing structurally deficient narrow bridge with a safer and wider bridge.
$308,000.00
$308,000.00
10/1/2008
7/1/2009
Plans COMPLETE. Dannenbaum is the consulting engineer.
1/12/2010: Plans are at 90% complete and right of way acquisition is underway.
 
6/21/2010: Plans are 90% complete. Right of Way acquisition underway.
 
1/04/2011: Barricades are being placed this week and they expect to begin construction the week of January 17th.
 
6/6/2011: Construction COMPLETE
 
http://maps.collincountytx.gov/bondrtr.html?pn=07107
6/17/2011 9:43 AM
Tracy Homfeld
07-108Collin County
CR 408 @ Tickey Creek
Engineering and Construction
$407,000.00
$407,000.00
2/1/2010
Binkley and Barfield is the consulting Engineer. 90%
2/22/2010: Binkley and Barfield's engineering contract and fee proposal was approved on 2-1-2010. They have begun work on the plans.
 
6/21/2010: Design is underway.
 
1/04/2011: Final comments have been addressed and I expect to have 90% plans in February.
 
6/6/2011: The plans are 90% complete. ROW acquisition underway.
 
11/1/2011: Verified by Special Projects Manager - Plans are 90% complete and the final parcel of Right of Way is being obtained. Anticipate Construction bidding to happen in the Spring of 2012.
 
COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07108
4/16/2013 3:55 PM
Tracy Homfeld
07-109Collin County
CR 655 @ Branch of Brushy Creek
Engineering and Construction
Replacing Existing metal Culverts with a concrete box culvert.
$308,000.00
$308,000.00
10/1/2008
Plans are complete. Dannenbaum is the consulting Engineer
Complete
2/22/2010: Plans are complete. We will advertise for bids in February 2010.
 
6/21/2010: Construction is underway. Anticipate completion in July 2010.
 
1/04/2011: Project was completed in July 2010. COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07109
6/17/2011 9:39 AM
Tracy Homfeld
07-110Collin County
CR 593 @ Price Creek
Engineering and Construction
Replacing 2-10 foot culverts with a 70 foot bridge.
$352,000.00
$352,000.00
10/1/2008
Gojer and Associates is the consulting engineer. Plans are Complete. No Right of Way is required.
7/1/2009
Complete
Construction COMPLETE
http://maps.collincountytx.gov/bondrtr.html?pn=07110
6/17/2011 9:40 AM
Tracy Homfeld
07-111Collin County
CR 58 @ Clarks Branch
Engineering and Construction
$693,000.00
$693,000.00
Funds reallocated to other projects.
http://maps.collincountytx.gov/bondrtr.html?pn=07111
12/11/2012 3:21 PM
Tracy Homfeld
07-112Collin County
CR 134 @ Honey Creek
Engineering and Construction
Replacing existing metal culverts with a bridge.
$374,000.00
$374,000.00
10/1/2008
Binkley and Barfield is the consulting Engineer. Plans are 90% Complete.
1/12/2010: Plans are 90% complete. Waiting on survey exhibits and descriptions to start acquiring Right of Way.
 
6/21/2010: Plans are 90% complete. Right of Way acquisition underway.
 
1/04/2011: Same as above.
 
6/6/2011: Plans are being finalized. Engineer is finalizing plans. Anticipate advertising for construction later this summer.
 
11/1/2011: Verified by Special Projects Manager - This contract was awarded to 2L Construction.  Construction is underway.
 
12/11/2012: Construction was completed in June 2012 
http://maps.collincountytx.gov/bondrtr.html?pn=07112
12/11/2012 3:51 PM
Tracy Homfeld
07-113Collin County
CR 580 @ Indian Creek
Engineering and Construction
$429,000.00
$429,000.00
Funding has been reallocated to other projects.
http://maps.collincountytx.gov/bondrtr.html?pn=07113
12/11/2012 3:51 PM
Tracy Homfeld
07-114Collin County
CR 463 @ Branch of Sister Groove Creek
Engineering and Construction
Replacing metal culvert with a concrete Box Culvert.
$308,000.00
$308,000.00
2/1/2010
Binkley and Barfield is the consulting Engineer. 95% Complete.
Binkley and Barfield's engineering contract and fee proposal was approved on 2-1-2010. They have begun work on the plans.
 
4/31/2010: Binkley and Barfield’s provided 95% plans the week of 4/19/2010.  ROW exhibits have not been received from their surveyor.
 
6/21/2010: Right of Way Exhibits have been received. Right of Way acquisition has begun.
 
1/04/2011: Jeske Construction was low bidder.  Work began in November. Project delayed due to City of Princeton Water Line relocation issue.  The City of Princeton agreed to reimburse us for the water line relocation and Jeske’s sub-contractor is in the process of relocating the water line at this time.  Construction on the box should resume next week.
 
6/17/2011: COMPLETE
 
http://maps.collincountytx.gov/bondrtr.html?pn=07105
6/17/2011 9:46 AM
Tracy Homfeld
07-115Collin County
SH 5
@ East Fork of the Trinity Bridge
Right-of-Way Only
COUNTY DISCRETIONARY PROJECT - 10% Right of Way participation with TxDOT.
$70,000.00
Right of Way participation project is COMPLETE
1/26/2011 8:47 AM
Tracy Homfeld
99-00-21Wylie
FM 1378
North of Parker RoadSouth of Parker Road
0.23
Engineering Only
Engineering for a 6 lane divided concrete roadway with curb and gutter at the intersection of Parker Road.
1/25/2011
30% Complete - Birkhoff, Hendricks and Carter are doing the plans.
4/26/2011: Verified by City Engineer. Preliminary alignment has been submitted to the City for review. City will meet with TxDOT to discuss project.
 
11/15/2011: Verified by City Engineer - The City has met with both TxDOT and NTMWD and they are pleased with the alignment. The consultant is proceeding with the construction plans which are at aound 30% complete.  City expects a 60% submittal next month.
 
1/23/2013: Design is complete. Project has received RTR funding for construction. Utility relocation is underway.
1/23/2013 10:49 AM
Tracy Homfeld
99-00-22Collin County
FM 1378
North of FarmsteadSouth of Stacy Rd.
Engineering Only
COUNTY DISCRETIONARY  - Preliminary Engineering and Env. document only for the section of FM 1378 from Farmstead to South of Stacy Road. Fairview is participating 50% of the cost.
 
No final engineering or construction funding is identified to date.
$63,735.49
$63,735.49
LAN contract has been approved.
1/26/2011: LAN has started on the preliminary Engineering.
 
6/17/2011: Engineering is ongoing. A public meeting is scheduled for July 26, 2011.
 
11/16/2011: Stakeholder Cities have expressed their desire to discontinue engineering on this project, therefore this project has been stopped.
11/16/2011 12:59 PM
Tracy Homfeld