   | County Road  | Description | Status  | Priority  | Completion Date  | Comments | Modified  | | View  | Miles  | Map |
|---|
| | Mailed easement documents on county tracts 4/12/12. | Not Started | (1) High | | From SH 289 east to CR 97. | | | General | .654 | |
| | Completed flex-base rock set-up 2/20/2012. | In Progress | (1) High | | From CR 513 south to CR 512. | | | General | .81 | |
| | Easement documents have been mailed out. | Not Started | (1) High | | From CR 1100 south to CR 982. | | | General | .21 | |
| | Previous ROW issues on various sections (rock portion). | Not Started | (1) High | | From CR 133 west and south to existing asphalt section. | | | General | 1.501 | |
| | Requires City of Celina cost participation. | Not Started | (1) High | | From CR 101 east to CR 128. | | | General | 1.0 | |
| | Requires City of Weston cost participation. | Not Started | (1) High | | From CR 171 southeast to FM 543. | | | General | .614 | |
| | Started creating required easement documents Mar. '12. | Not Started | (1) High | | From CR 210 south to CR 206. | | | General | 2.09 | |
| | Requires City of Melissa cost participation. | Not Started | (1) High | | From CR 206 east to CR 277. | | | General | .92 | |
| | McKinney is unable to cost participate in FY-2012. | On Hold | (1) High | | From CR 338 east & north to asphalt. (Requires City of McKinney participation) | | | General | 1.74 | |
| | Green Construction Folder was released 3/15/2012. | Not Started | (1) High | | From SH 5 west / south to CR 371. | | | General | 1.16 | |
| | Started crossroad culvert installations 12/13/2011. | In Progress | (1) High | | From CR 375 south to CR 373. | | | General | .79 | |
| | Bond Project Rd. | In Progress | (1) High | | From FM 75 west to New Hope city limits. | | | General | 2.83 | |
| | Starting flex-base set-up on 3/14/2012. | In Progress | (1) High | | From CR 469 north to CR 471. | | | General | .56 | |
| | Completed final flex-base set-up 5/15/2012. | In Progress | (1) High | | From CR 439 north to CR 442. | | | General | 1.05 | |
| | Released construction folder to Utility Coord. 2/24/2012. | Not Started | (1) High | | From FM 982 north to CR 392. | | | General | 1.46 | |
| | City of Princeton is cost participating on this project. | Not Started | (1) High | | From CR 490 west existing asphalt section. | | | General | 1.65 | |
| | Required easement documents have been mailed out. | Not Started | (1) High | | From CR 466 north to existing asphalt. | | | General | 1.28 | |
| | Required easement document has been mailed out. | Not Started | (1) High | | From CR 465 west / south loop back to CR 465. | | | General | .21 | |
| | Completed clearing required ROW on 5/7/2012. | In Progress | (1) High | | From FM 545 north and west to CR 472. | | | General | 1.95 | |
| | Completed flex-base rock set-up 2/23/2012. | In Progress | (1) High | | From FM 2862 east to CR 577. | | | General | 1.56 | |
| | Completed two-course asphalt paving on 5/10/2012. | Completed | (1) High | | From FM 3133 east to CR 525. | | | General | 1.14 | |
| | Completed two-course asphalt paving on 5/10/2012. | Completed | (1) High | | From CR 525 east to existing asphalt. | | | General | 1.63 | |
| | Waiting on release from utility companies (March 2012 ). | In Progress | (1) High | | From US HWY 380 south to SH 78. | | | General | 1.96 | |
| | Required easement documents have been mailed out. | Not Started | (1) High | | From CR 613 west to CR 610. | | | General | .84 | |
| | Completed two-course asphalt paving on 10/25/2011. | Completed | (1) High | | From SH 78 west and north to CR 574. | | | General | 3.23 | |
| | Completed two-course asphalt paving on 5/8/2012. | Completed | (1) High | | From CR 534 north to Grayson Cty. line. | | | General | .12 | |
| | Completed final flex-base set-up & surface slush 10/25/2011. | In Progress | (1) High | | From FM 1138 east to the first corner. | | | General | 1.02 | |
| | Mailed out required ROW easement documents 7/2011. | Not Started | (1) High | | From CR 567 north to CR 565. | | | General | 1.42 | |
| | Started crossroad culvert installations 2/28/2012. | In Progress | (1) High | | From CR 665 east to Hunt County. | | | General | 1.90 | |
| | Completed two-course asphalt paving on 10/7/2011. | Completed | (1) High | | From CR 619 east to cul-de-sac. | | | General | .22 | |
| | Waiting on three ROW easement documents (2/10/12). | Not Started | (1) High | | From FM 981 south to CR 825. | | | General | 1.33 | |
| | Completed crossroad culvert installation 1/04/2012. | In Progress | (1) High | | From FM 1777 east to Hunt. Co. Rd. 2670 | | | General | .68 | |
| | Completed ROW clearing on 2/23/2012. | In Progress | (1) High | | From existing asphalt east to Hunt County. | | | General | .34 | |
| | | Not Started | (1) High | | From CR 610 east to cul-de-sac. | | | General | .42 | |
| | Started sub-grade / dirt work 5/17/2012. | In Progress | (1) High | | From CR 696 east to Hunt Cty. line. | | | General | .48 | |
| | Completed two-course asphalt paving on 10/7/2011. | Completed | (1) High | | From CR 619 south to CR 572. | | | General | .78 | |
| | Mailed out required easement documents 12/6/2011. | Not Started | (1) High | | From FM 3356 west to cul-de-sac. | | | General | .44 | |
| | | Not Started | (1) High | | From CR 465 east to end of road at the cemetery. | | | General | .13 | |