   | County Road  | Description | Status  | Priority  | Completion Date  | Comments | Modified  | | View  | Miles  | Map |
|---|
| | Mailed easement documents on 4/12/12. | Not Started | (1) High | | From SH 289 east to CR 97. | | | General | .654 | |
| | Required right-of-way document has been mailed out. | On Hold | (1) High | | From CR - 471 south ending at the Verona Cemetery. | | | General | .24 | |
| | Required documents are being created (Dec. 2012). | Not Started | (1) High | | From CR - 330 north to cul-de-sac. | | | General | .43 | |
| | Completed flex-base rock set up March 2013. | In Progress | (1) High | | From CR - 431 north to existing pavement. City of Garland's section is not part of the upgrade project. | | | General | .55 | |
| | Right-of-way easement documents mailed out Dec. 2012. | Not Started | (1) High | | From CR - 490 intersection, both east and west to each end of road. | | | General | .44 | |
| | Easement documents have been mailed out. | Not Started | (1) High | | From CR 1100 south to CR 982. | | | General | .21 | |
| | FDR and resurface from FM 1827 east to end of road | On Hold | (2) Normal | | Letters mailed to property owners and residents. | | | General | .33 | |
| | Re-mailed required right-of-way documents 12/2012. | Not Started | (1) High | | From CR 133 west and south to existing asphalt section. | | | General | 1.501 | |
| | Started required right-of-way clearing March 2013. | In Progress | (1) High | | From CR 101 east to CR 128. | | | General | 1.0 | |
| | Bond Project. Utilities are being scheduled for relocation. | In Progress | (1) High | | FRom CR - 169 east to existing pavement. | | | General | 1.49 | |
| | Mutual Boundary Road with City of Weston. | On Hold | (1) High | | From CR 171 southeast to FM 543. | | | General | .614 | |
| | Completed crossroad culvert installations 5/1/2013. | In Progress | (1) High | | From CR 210 south to CR 206. | | | General | 2.09 | |
| | Released construction folder to Utility Coord. 4/16/13. | Not Started | (1) High | | From FM 3356 east to end of road, "No Outlet". | | | Department | .68 | |
| | Need to re-mail right-of-way documents. | Not Started | (1) High | | From CR - 283 south US 75 Service Rd. | | | General | 3.55 | |
| | Requires City of Melissa cost participation. | Not Started | (1) High | | From CR 206 east to CR 277. | | | General | .92 | |
| | Construction Folder released to Utility Coord. 12/21/12. | Not Started | (1) High | | From CR - 289 east and north to existinbg pavement. | | | General | 4.35 | |
| | On FY -2013 Upgrade List, will require some right-of-way. | Not Started | (1) High | | From CR 338 east & north to asphalt. (Requires City of McKinney participation) | | | General | 1.74 | |
| | Completed two-course asphalt paving 5/8/2013. | Completed | (1) High | | From SH 5 west / south to CR 371. | | | General | 1.16 | |
| | Completed two-course asphalt paving 5/8/2013. | Completed | (1) High | | From CR 375 south to CR 373. | | | General | .79 | |
| | Scheduling required right-of-way clearing approx. 6/1/2013. | In Progress | (1) High | | From FM 546 east to existing pavement. | | | General | 1.29 | |
| | Started replacing required culverts March 2013. | In Progress | (1) High | | From CR - 447 west to CR - 401. | | | General | 1.56 | |
| | Ready to schedule construction April 2013. | Not Started | (1) High | | From US 380 south to CR - 400. | | | General | 1.6 | |
| | ROW documents mailed out Dec. 2012. | On Hold | (1) High | | From Bridgefarmer Rd. west to Lowry Crossing city limits. | | | General | .83 | |
| | Started flex-base rock set-up 4/23/2013. | In Progress | (1) High | | From FM 75 west to New Hope city limits. | | | General | 2.83 | |
| | Completed 1st lift of flex-base rock 1/4/2013. | Not Started | (1) High | | From CR - 421south to concrete street. | | | General | 1.19 | |
| | Completed required right-of-way clearing 5/8/2013. | In Progress | (1) High | | From SH 5 east to CR - 419. | | | General | 1.75 | |
| | Completed crossroad culvert installation 5/8/2013. | Not Started | (1) High | | Fro SH 5 west to CR - 423, and from SH 5 east and south to CR - 421. | | | General | 1.29 | |
| | Project folder released to Utility Coordinator 4/16/2013. | Not Started | (1) High | | From existing asphalt south and east to existing pavement. | | | General | 1.24 | |
| | Started clearing required right-of-way April 15, 2013. | In Progress | (1) High | | From FM 982 north to CR 392. | | | General | 1.46 | |
| | Completed two-course asphalt paving 5/1/2013. | Completed | (1) High | | Section from CR 972 north to FM 1827. | | | General | 1.28 | |
| | Completed two-course asphalt paving 5/1/20132. | Completed | (1) High | | From CR 465 west / south loop back to CR 465. | | | General | .21 | |
| | Scheduling sub-grade / flex-base set-up 5/13/2013. | In Progress | (1) High | | From FM 2862 west to CR - 475. | | | General | .58 | |
| | Released Construction Folder to Utility Coord. 4/23/13. | Not Started | (1) High | | From FM 428 south to CR - 51. | | | General | 1.26 | |
| | Waiting on utilities to be relocated (April 2013). | Not Started | (1) High | | From CR - 525 east to CR - 574. | | | General | .37 | |
| | Re-mailed easement documents on 5/1/2013. | Not Started | (1) High | | From FM 6 north to end of road at Bear Creek Cemetery. | | | General | .88 | |
| | Need right-of-way for a cul-de-sac at end of road. | On Hold | (1) High | | From SH 78 west to end. | | | General | .37 | |
| | Completed last section of flex-base rocking 5/9/2013. | In Progress | (1) High | | From US HWY 380 south to SH 78. | | | General | 1.96 | |
| | Received all required right-of-way documents 3/2013. | Not Started | (1) High | | From FM 455 (Walnut St.) north and west to FM 455. | | | General | 1.37 | |
| | Re-sent easement documents ( Dec. 2012 ). | Not Started | (1) High | | From FM 2756 north to existing pavement. | | | General | 1.59 | |
| | Required utilities have been relocated (April 2013). | Not Started | (1) High | | From CR - 529 north and east to existing pavement. | | | General | 1.33 | |
| | Required right-of-way documents have been mailed out. | On Hold | (1) High | | From CR - 601 west and south to CR - 566. | | | General | 1.84 | |
| | Mailed out required ROW documents 7/2011. | On Hold | (1) High | | From CR 567 north to CR 565. | | | General | 1.42 | |
| | Flex-base rock set-up completed Dec. 2012. | In Progress | (1) High | | From CR 665 east to Hunt County. | | | General | 1.90 | |
| | FDR and resurface from Farmersville City limits (East of ballpark on Murchison) east and north to CR 656 | In Progress | (2) Normal | | FDR has been completed. Stabilization process is progressing. A surface will be applied when the stabilization process is complete and weather allows. | | | General | | |
| | Started flex-base rock set-up on 4/29/2013. | In Progress | (1) High | | From FM 1777 east to Hunt. Co. Rd. 2670 | | | General | .68 | |
| | Completed flex-base rock set-up 4/11/2013. | In Progress | (1) High | | From existing asphalt east to Hunt County. | | | General | .34 | |
| | Ready to schedule right-of-way clearing. | Not Started | (1) High | | From FM 2194 east and north to FM 2194. | | | General | .73 | |
| | | Not Started | (1) High | | From CR 610 east to cul-de-sac. | | | General | .42 | |
| | Started final flex-base rock set-up 4/2/2013. | In Progress | (1) High | | From CR 696 east to Hunt Cty. line. | | | General | .48 | |
| | Ready to schedule required ROW clearing. | In Progress | (1) High | | From FM 3356 west to cul-de-sac. | | | General | .44 | |
| | Completed two-course asphalt paving 5/1/2013. | Completed | (1) High | | From CR 465 east to end of road at the cemetery. | | | General | .13 | |