 |    | Project ID  | Managing Entity  | Jurisdiction  | Project Name  | From  | To  | | Project Type  | Project Description | Lanes - Existing  | Lanes - Proposed  | | | | | Engineering Start Date  | Engineering End Date  | Engineering Status  | Construction Start Date  | Construction End Date  | Construction Status  | NCTCOG Contract On file  | Comments | Map  | Modified  | |
|---|
 | | | | | | | | | | | | | | | | | | | | | | | | | | | |  Managing Entity : Allen (2) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 20081 | Allen | On TxDOT Road System | | Rockridge Road | South of Stacy Rd. | | Engineering and Construction | Reconstruct 2 lane roadway to a 6 lane roadway
| 2 | 6 | $6,967,339.00 | | $5,573,871.00 | $1,393,468.00 | | | | | | | | All parties (TxDOT, Allen, Fairview, County and LAN) are working on an agreement to start preliminary design and Enviromental document and continue onto the PS&E. | http://maps.collincountytx.gov/rtrbond.html?rtr=20081 | | |  | | 20082 | Allen | On TxDOT Road System | | Angel Parkway | FM 1378 | | Engineering and Construction | Reconstruct 2 lane roadway to a 4 lane divided roadway
| 2 | 4 | $8,227,689.00 | $6,279,643.00 | $400,000.00 | $1,548,046.00 | | | | | | | | TxDOT is doing Design in House. Schematic has been approved. Env. Document in Final Stages. Should be cleared by FHWA witin the month. Let date is Sept 2012. 2007 Collin County bond funds available ($490,000) | http://maps.collincountytx.gov/rtrbond.html?rtr=20082 | | |  Managing Entity : Collin County (2) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 20075 | Collin County | Off TxDOT Road System | | FM 544 | FM 3412 | | Construction Only | Realign on new location and widen existing 2 lane to 6 lane divided. | 2 | 6 | $3,233,598.46 | $7,463,905.00 | | $1,865,976.00 | | | | | | | | RTR FUNDING RECEIVED. ILA approved with City of Wylie and funds in the amount of $3.233.598.46 were sent to Wylie on 7-30-2010. Construction is underway and being managed by the City of Wylie. Bond project #99-102 funded this for Engineering.
1/11/2011: The City did a final walk through on the project a couple of weeks ago. TxDOT opens the entire roadway in March.
The Construction cost came under the approved RTR dollars so savings will be reallocated to other projects. | http://maps.collincountytx.gov/rtrbond.html?rtr=20075 | | |  | | 20089 | Collin County | Off TxDOT Road System | | US 75 | SH 121 | | Construction Only | Construct new two lane service road
| 0 | 2 | $15,000,000.00 | $12,000,000.00 | | $3,000,000.00 | | | COMPLETE | | | | | Design by HNTB is complete. Pre bid meeting was held on Oct. 6, 2010. Bond funds available in the amount of $5,025,000 #07-094. | http://maps.collincountytx.gov/rtrbond.html?rtr=20089 | | |  Managing Entity : DART (2) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 11141.2 | DART | Off TxDOT Road System | | | | | Construction Only | Surface Parking expansion to include 380 more parking spaces | | | $1,703,750.00 | $415,000.00 | | $103,750.00 | | | | | | | | Other funds in the amount of $1,185,000 avail. for this project. | | | |  | | 20069 | DART | Off TxDOT Road System | | West Side of North Dallas Tollway | (Between) Tennyson Pkwy and Spring Creek Pkwy | | Park and Ride | Provide 544 (ultimately 716) space DART Park and Ride facility. Funding is for Construction.
| | | $12,700,000.00 | $8,500,000.00 | | $4,200,000.00 | | | | | | | | | http://maps.collincountytx.gov/rtrbond.html?rtr=20069 | | |  Managing Entity : Frisco (3) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 20086 | Frisco | On TxDOT Road System | | | | | Intersection Improvement | Design and construct a right turn bay on the South bound frontage road of SH 121 at Ohio Drive
| | | $294,468.00 | $235,574.00 | | $58,894.00 | | | | | | | | Local Let by City of Frisco. TxDOT will handle permitting on frontage rds. Estimated Let date for this project is Nov 2013. | http://maps.collincountytx.gov/rtrbond.html?rtr=20086 | | |  | | 20087 | Frisco | On TxDOT Road System | | SH 121 | FM 3537 | | Intersection Improvement | Add turning bays at intersections; signal improvements, add ADA compliant ramps, and pedestrian signals
| | | $3,735,085.00 | $2,988,067.00 | | $747,018.00 | | | | | | | | Frisco to manage for TxDOT through agreement. Estimated Let date for this project is Aug 2013. | http://maps.collincountytx.gov/rtrbond.html?rtr=20087 | | |  | | 20207 | Frisco | Off TxDOT Road System | | Legacy Drive | Longhorn Trail | | Construction Only | CONSTRUCT 2 LANE RURAL DIVIDED ARTERIAL | 0 | 2 | $14,257,471.00 | $14,257,471.00 | | | | | Design Underway | | | | | Plans are currently 80% complete | http://maps.collincountytx.gov/rtrbond.html?rtr=20207 | | |  Managing Entity : McKinney (1) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 20093 | McKinney | On TxDOT Road System | | Eldorado Pkwy (FM 546) | McDonald (SH 5) at Tennessee, From 1000 ft in each direction. | | Intersection Improvement | ADD RIGHT TURN LANES IN EACH DIRECTION AT THE INTERSECTION; AND ADD RAISED MEDIAN TO THE INTERSECTION OF MCDONALD STREET/SH 5 AT TENNESSEE STREET
| | | $2,344,152.00 | $1,875,321.00 | | $468,831.00 | | | | | | | | TxDOT is going Design in house. Let date of Aug 2011. Schematic submittal is forthcoming. | http://maps.collincountytx.gov/rtrbond.html?rtr=20093 | | |  Managing Entity : North Central Texas Council of Governments (4) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 20053 | North Central Texas Council of Governments | Off TxDOT Road System | | | | | Transit | PHASE 1 - LIGHT RAIL. Project Incldes Engineering/Planning. | | | $625,000.00 | | $500,000.00 | $125,000.00 | | | | | | | | Preliminary Engineering underway. Fund Phase 1; Fixed Funded; planning work for DART's red line from City of McKinney to City of Anna to be funded under regular UPWP planning studies.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20053 | | |  | | 20054 | North Central Texas Council of Governments | Off TxDOT Road System | | DFW International Airport | North Central / Red line (Colin County Section) | | Transit | TRANSIT - PROVIDE A KEY EAST-WEST PASSENGER RAIL LINK ACROSS THE NORTHERN PART OF THE DART SERVICE AREA
| | | $1,250,000.00 | $1,000,000.00 | | $250,000.00 | | | | | | | | Preliminary Engineering Underway. | http://maps.collincountytx.gov/rtrbond.html?rtr=20054 | | |  | | 20070 | North Central Texas Council of Governments | Off TxDOT Road System | | Denton / Collin County line | North Frisco (Collin County Section) | | Transit | PHASE 1 - RAIL TRANSIT (PASSENGER RAIL) | | | $1,875,000.00 | $1,500,000.00 | | $375,000.00 | | | | | | | | Preliminary Engineering Underway. | http://maps.collincountytx.gov/rtrbond.html?rtr=20070 | | |  | | 20088 | North Central Texas Council of Governments | Off TxDOT Road System | | Denton County Line | Rockwall County Line | 55.00 | Engineering Only | Environmental clearance for construction of Outer Loop
| | | $6,250,000.00 | $5,000,000.00 | | $1,250,000.00 | | | | | | | | NCTCOG has completed the Locally approved Environemental document for Segment 1 (US 75 - SH 121). It was approved by the Collin County Toll Road Authority Summer 2010. COG is currently working on the Env. Document for Seg 3 (Denton County Line to US 75). | http://maps.collincountytx.gov/rtrbond.html?rtr=20088 | | |  Managing Entity : Plano (8) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 20050 | Plano | Off TxDOT Road System | | @ Independence Pkwy, Custer Rd and US 75 (Service Rd.) | | | Intersection Improvement | Dual left lanes, Dedicated right lanes, consolidate split intersections into a normalized intersection. Funding is for Engineering and Construction.
| | | $3,029,934.00 | $2,423,947.00 | | $605,987.00 | | | | | | | | Plano is negotiating consulting engineering contract. | http://maps.collincountytx.gov/rtrbond.html?rtr=20050 | | |  | | 20056 | Plano | Off TxDOT Road System | | K Avenue | Ridgewood Dr. | | Construction Only | Reconstruct existing 4 lane divided and 6 lane divided road sections. Project Funding Includes Right-of-Way and Construction.
| 4/6 | 4/6 | $7,354,880.00 | $5,883,904.00 | | $1,470,976.00 | | | | | | | | Design by Teage, Nall and Perkins. Engineering is complete. Construction began in March 2010 and will be completed in 16 months. The north side paving from K to Jupiter is almost completed and traffic will be switched in November 2010. Collin County ILA reallocated $1,550,000 from US 75 Ramps. Will reallocate $900,000 from the 2007 bond project to another project. This is available for local contribution. | http://maps.collincountytx.gov/rtrbond.html?rtr=20056 | | |  | | 20058 | Plano | Off TxDOT Road System | | @ Coit, Independence Pkwy and Alma Rd. | | | Intersection Improvement | Funding for Engineering, Right-of-Way and Construction. Project will include Adding Dual left Lanes. | | | $1,734,842.00 | $1,387,874.00 | | $346,968.00 | | | | | | | | Preliminary Engineering for schematic is underway. | http://maps.collincountytx.gov/rtrbond.html?rtr=20058 | | |  | | 20059 | Plano | Off TxDOT Road System | | Coit Rd. | Jupiter Road | | Intersection Improvement | Add dual left lanes, right lanes, remove road hump, maximize left lane lengths. Project includes funding for Engineering, Right-of-Way and Construction.
| | | $2,347,097.00 | $1,877,677.00 | | $469,420.00 | | | | | | | | The schematic and egineering contract have been approved by the Plano city council. The consultant is beginning design. | http://maps.collincountytx.gov/rtrbond.html?rtr=20059 | | |  | | 20060 | Plano | Off TxDOT Road System | | Custer Rd. | K Avenue | | Intersection Improvement | Add right turn lanes and dual left turn lanes. Funding is for the Engineering, Right-of-way and Construction.
| | | $1,454,225.00 | $1,163,380.00 | | $290,845.00 | | | | | | | | The City of Plano is working with the engineering consultant on a contract for the schematic. | http://maps.collincountytx.gov/rtrbond.html?rtr=20060 | | |  | | 20061 | Plano | Off TxDOT Road System | | 15th St. | Parker Rd. | | Intersection Improvement | Realign traffic lanes to increase traffic flow, optimize signal timing, add right lanes. Funds are for Engineering, Right-of-Way and Construction.
| | | $1,771,661.00 | $1,417,329.00 | | $354,332.00 | | | | | | | | Plano City Council will approve schematic and engineering contract on October 11, 2010. | http://maps.collincountytx.gov/rtrbond.html?rtr=20061 | | |  | | 20063 | Plano | Off TxDOT Road System | | Ohio Dr. | SH 121 | | Construction Only | Widen existing 2 lane sections to 6 lanes and construct East and West sides to complete the 6 lane divided thoroughfare road.
| | | $5,408,000.00 | | $4,326,400.00 | $1,081,600.00 | | | Engineering Completed by City using County 2003 Bond Funds | | | | | Construction is completed. Collin County Bond Project #03-063 $1,050,000 with an additional reallocation of $330,000 from 03-045 for total county participation in Engineering of ($1,380,000). | http://maps.collincountytx.gov/rtrbond.html?rtr=20063 | | |  | | 29002 | Plano | Off TxDOT Road System | | | | | | Credits from the City of Plano's contribution on SH 121. Placeholder for Future Project. | | | $1,890,927.00 | $1,890,927.00 | | | | | | | | | | Project to be identified at a later date. | | | |  Managing Entity : Richardson (3) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 20051 | Richardson | Off TxDOT Road System | | US 75 along Prairie Creek | DART Bush Turnpike Station | | Bicycle/Pedestrian | Construction of a new 12 foot wide concrete trail.Funding is for Eng. and Construction.
| | | $2,434,552.00 | $1,947,641.00 | | $486,911.00 | | | | | | | | This funding is for Trails B&C. Trail B is under Construction. Trail C will be under construction by the end of 2010.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20051 | | |  | | 20052 | Richardson | Off TxDOT Road System | | Alma Road and SH 190 | Spring Creek Nature Area and Panther Creek | | Bicycle/Pedestrian | Construct 10 to 12 foot wide trail. Construction funding only.
| | | $456,219.00 | $364,975.00 | | $91,244.00 | | | | | | Under construction | | This funding is for Trails A&B. Currently Under Construction.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20052 | | |  | | 20068 | Richardson | Off TxDOT Road System | | @ Alma, @ Jupiter (from Alma Dr.), @ SH 190 (to Jupiter at SH 190/PGBT) | | | Intersection Improvement | Additional left turn lanes and/or a right turn bay. Funding includes Engineering, Right-of-way and Construction.
| | | $1,156,532.00 | $925,226.00 | | $231,306.00 | | | Ongoing | | | | | Design is underway. | http://maps.collincountytx.gov/rtrbond.html?rtr=20068 | | |  Managing Entity : TxDOT Dallas (41) |  | | | | | | | | | | | | | | | | | | | | | | | | | | | |  | | 11540 | TxDOT Dallas | On TxDOT Road System | | @ Parker Rd. | | | Intersection Improvement | Reconstruct interchange as single point urban interchange TxDOT CSJ# 0047-06-134 | | | $24,348,556.00 | $17,083,845.00 | | $0.00 | | | | | | | | This has other funds in the amount of $7,264,711.
Under construction. Expected completeion date is Dec 2010. County Bond Project #03-046 participated $6,000,000. $2,684,711 sent directly to TxDOT on 3-27-08. The remainder to City of Plano.
| http://maps.collincountytx.gov/rtrbond.html?rtr=11540 | | |  | | 11716 | TxDOT Dallas | On TxDOT Road System | | PGBT | Park Blvd. | | Engineering and Construction | WIDEN DIRECT CONNECT RAMPS FROM PGBT TO NB US 75 AND FROM SB US 75 TO THE PGBT; WIDEN THE DART RR BRIDGE AND PLANO PARKWAY BRIDGE UNDERPASSES; CONSTRUCT AN AUXILIARY LANE ON NB US 75 TO THE PARK BOULEVARD EXIT RAMP.
TxDOT CSJ# 0047-06-133
| | | $25,920,000.00 | $14,970,000.00 | $1,500,000.00 | $2,500,000.00 | | | | | | | | This project has other funds in the amount of $6,950,000
Trans-Systems is doing Design. Schematic is under MAJOR Revision. Let Date Sept 2012.
| http://maps.collincountytx.gov/rtrbond.html?rtr=11716 | | |  | | 11718 | TxDOT Dallas | On TxDOT Road System | | Dallas Collin County Line | Spring Creek Parkway | | Engineering and Construction | Widen 4 lane divided urban to 6 lane divided urban. TXDOT CSJ# 0281-02-060
| 4 | 6 | $10,527,846.00 | $5,084,600.00 | $500,000.00 | $1,365,569.00 | | | | | | | | This project has other funds in the amount of $3,577,677.
Currently under construction. | http://maps.collincountytx.gov/rtrbond.html?rtr=11718 | | |  | | 11719.1 | TxDOT Dallas | On TxDOT Road System | | SH 5 | East of Angel Parkway | | Construction Only | WIDEN 2 TO 4 LANE DIVIDED WITH INTERSECTION IMPROVEMENTS AT FM 2786 AND US 75, GREENVILLE RD, ANGEL PKWAY. TxDOT CSJ# 3392-01-008 | 2 | 4 | $6,789,040.00 | $2,250,000.00 | | $4,539,040.00 | | | | | | | | Still waiting on the Environmental Assessment (EA) document to go to the Federal Highway Administration (FHWA). Should be within the month. Will Let with Stacy Road from Angel to FM 1378 in Sept 2012. | http://maps.collincountytx.gov/rtrbond.html?rtr=11719.1 | | |  | | 11728 | TxDOT Dallas | On TxDOT Road System | | US 380 | Stonebridge Drive | | Construction Only | WIDEN RURAL 2 LANE UNDIVIDED TO 6 LANE URBAN DIVIDED; EXPAND INTERSECTION INCLUDING LEFT TURN LANES; AND INTERSECTION IMPROVEMENTS AT US 380 AND FM 2478/CUSTER RD. TxDOT CSJ# 2351-01-013 | 2 | 6 | $15,479,000.00 | $3,200,000.00 | | | | | | | | | | Other funds in the amount of $12,279,000 are available for this project. (Collin County participated $6,250,000 through bond project #03-035 and $2,800,000 through bond project #07-035. A total of $9,050,000 was sent to City of McKinney in Oct. 2008.)
Under Construction. Expected completion date early 2012.
| http://maps.collincountytx.gov/rtrbond.html?rtr=11728 | | |  | | 20008 | TxDOT Dallas | On TxDOT Road System | | Preston Rd. (SH 289) | Custer Rd. (FM 2478) | | Engineering and Construction | Widen 2 lane Rural to 6 lane Divided Urban Highway.
TxDOT CSJ# 0135-12-025 | 2 | 6 | $28,475,353.00 | $28,245,353.00 | | $230,000.00 | | | 90% Complete | | | | | Design is 90% complete. TxDOT is waiting on Right Of Way to proceed. Let date is June 2011. | http://maps.collincountytx.gov/rtrbond.html?rtr=20008 | | |  | | 20012 | TxDOT Dallas | On TxDOT Road System | | East of Dallas North Tollway | Coit Road (CR 72 / CR 74) | | Engineering and Construction | WIDEN 4 TO 6 LANES DIVIDED; ADD NEW 4/6 LANE ACCESS ROADS AT GRADE SEPARATION; CONSTRUCT GRADE SEPARATION AT US 380 AND SH 289. CSJ# 0135-02-044 | 4 | 6 | $63,853,150.00 | $51,082,520.00 | | $12,770,630.00 | | | | | | | | Collin County is managing the AECOM Preliminary Engineering contract. Had a Value Engineering Study to discuss alternatives for the Schematic in Sept. 2009. Public meeting was held in July 2010. | http://maps.collincountytx.gov/rtrbond.html?rtr=20012 | | |  | | 20013 | TxDOT Dallas | On TxDOT Road System | | West of CR 26 (Denton County Line) | East of Dallas North Tollway | | Engineering and Construction | WIDEN 4 TO 6 LANES DIVIDED, ADD NEW 4/6 LANE ACCESS ROADS AT GRADE SEPARATION; CONSTRUCT GRADE SEPARATION AT US 380 AND DNT. TxDOT CSJ# 0135-11-018 | 4 | 6 | $34,489,648.00 | $27,591,719.00 | | $6,897,929.00 | | | | | | | | Had a Value Engineering Study to discuss alternatives for the Schematic in Sept. 2009. Collin County is managing the AECOM preliminary Engineering contract. (LAN doing grade separation at SH 289 final design). | http://maps.collincountytx.gov/rtrbond.html?rtr=20013 | | |  | | 20014 | TxDOT Dallas | On TxDOT Road System | | Business 78 | FM 6 | | Engineering and Construction | Widen 2 Lane Rural to 6 Lane Urban Divided. TxDOT CSJ#0281-01-030
| 2 | 6 | $15,124,855.00 | | $15,124,855.00 | | | | | | | | | Let date is April 2012. TxDOT is doing final Engineering in house at the District Office. Project will Let with CSJ# 0281-02-063 (SH 78 from SH 205 to Business SH 78). Final Plan are 45% complete | http://maps.collincountytx.gov/rtrbond.html?rtr=20014 | | |  | | 20019 | TxDOT Dallas | On TxDOT Road System | | Legacy Dr. | Spur 399 / SH 121 South | | Engineering and Construction | WIDEN 6 TO 8 MAINLANES AND 2 TO 3 FRONTAGE ROADS. TxDOT CSJ# 0047-06-139
| 6 | 8 | $78,842,561.00 | | $63,074,049.00 | $15,768,512.00 | | | | | | | | Preliminary Design Meetings to discuss Scope for the schematic have been held. TxDOT is going to hire a consultant to do the Engineering. Little Right of Way will be required. The Let date is Sept 2012. | http://maps.collincountytx.gov/rtrbond.html?rtr=20019 | | |  | | 20020 | TxDOT Dallas | On TxDOT Road System | | Spur 399 (SH 121 south) | Wilson Creek | | Construction Only | RECONSTRUCT AND WIDEN FROM 4 TO 8 LANES WITH 2 HOV CONCURRENT LANES AND 3 LANE FRONTAGE ROADS. TxDOT CSJ# 0047-06-108
| 4 | 8 | $54,185,305.00 | $48,368,244.00 | | $5,817,061.00 | | | | | | | | HDR is doing Design. Let date is March 2011. | http://maps.collincountytx.gov/rtrbond.html?rtr=20020 | | |  | | 20021 | TxDOT Dallas | On TxDOT Road System | | South of Bloomdale Road | North of US 380 | | Engineering and Construction | RECONSTRUCT AND WIDEN FROM 4 LANES TO 8 LANES; RECONSTRUCT FRONTAGE ROADS FROM 2 LANES TO 3 LANES. TxDOT CSJ# 0047-14-065
| 4 | 8 | $44,650,000.00 | $31,380,000.00 | | $7,720,000.00 | | | | | | | | Additional funds in the amount of $5,550,000 available for this project.
Already Let (May 2010) is effectively under construction, but contractor has not broke ground yet.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20021 | | |  | | 20022 | TxDOT Dallas | On TxDOT Road System | | SH 205 | Business 78 | | Engineering and Construction | Widen 2 Lane Rural to 6 Lane Divided Urban. TxDOT CSJ#0281-02-063
| 2 | 6 | $20,485,446.00 | | $20,485,446.00 | | | | | | | | | Let date is April 2012. TxDOT is doing Final Engineering in house. (District Office) Will let with 0281-01-030, The Final Engineering Plans are at 45% complete. | http://maps.collincountytx.gov/rtrbond.html?rtr=20022 | | |  | | 20031 | TxDOT Dallas | On TxDOT Road System | | Wilson Creek | US 380 | | Engineering and Construction | RECONSTRUCT FROM 4 TO 8 LANES; RECONSTRUCT FRONTAGE ROADS FROM 2 LANES TO 2/3 LANES. TxDOT CSJ# 0047-14-046.
| 4 | 8 | $49,422,238.00 | $39,537,790.00 | | $7,016,605.00 | | | | | | | | Other funds in the amount of $2,867,843 are available for this project.
HDR is doing Design. Let date is March 2011. | http://maps.collincountytx.gov/rtrbond.html?rtr=20031 | | |  | | 20032 | TxDOT Dallas | On TxDOT Road System | | US 75 Northbound Frontage Rd. | SH 5 | | Engineering and Construction | Widen 2 lane rural to 4 lane (ultimate 6 lane) urban roadway. TxDOT CSJ# 0816-04-044
| 2 | 4/6 | $14,090,554.00 | $8,372,443.00 | $3,200,000.00 | $2,518,111.00 | | | | | | | | Collin County is managing the design contract with Dannenbaum Engineering. Project was Environmentally cleared summer 2010. Dannenbaum is doing Final Design. Just submitted 30% for review. Let date is June 2012. | http://maps.collincountytx.gov/rtrbond.html?rtr=20032 | | |  | | 20033 | TxDOT Dallas | On TxDOT Road System | | US 380 | Panther Creek | | Construction Only | Reconstruct and widen 2 lane rural highway to 6 lane divided urban. TxDOT CSJ: 0091-04-041
| 2 | 6 | $22,210,993.00 | $18,131,423.00 | | $2,266,428.00 | | | | | | | | Other funds in the amount of $1,813,142.
Under construction. Expected completion date is early 2012. | http://maps.collincountytx.gov/rtrbond.html?rtr=20033 | | |  | | 20034 | TxDOT Dallas | On TxDOT Road System | | Panther Creek | FM 3537 | | Construction Only | Reconstruct and widen 2 lane rural highway to 6 lane divided urban. TxDOT CSJ# 0091-05-041
| 2 | 6 | $10,279,541.00 | $5,669,315.00 | $3,000,000.00 | $708,665.00 | | | | | | | | Other funds in the amount of $901,561 available.
Under construction. Expected completion date is early 2012 | http://maps.collincountytx.gov/rtrbond.html?rtr=20034 | | |  | | 20035 | TxDOT Dallas | On TxDOT Road System | | FM 544 | FM 2514 | | Engineering and Construction | Reconstruct and widen 2 lane rural to 6 lane urban. TxDOT CSJ# 2056-01-045
| 2 | 6 | $21,574,891.00 | $15,377,288.00 | | $6,072,603.00 | | | | | | | | this project has other funds in the amount of $125,000.
Currently Under Design. ENV. on hold in Austin due to ROW issues. City of Murphy working with Half Assoc to resolve issues. Collin County Managing Eng. with CP&Y. Have recently started back up with design. ENV. Clearance is expected soon. | http://maps.collincountytx.gov/rtrbond.html?rtr=20035 | | |  | | 20036 | TxDOT Dallas | On TxDOT Road System | | Spring Creek Pkwy | SH 205 | | Engineering and Construction | RECONSTRUCT AND WIDEN 2 LANE TO 6 LANE URBAN. txDOT CSJ# 0281-02-039
| 2 | 6 | $27,429,047.00 | $17,303,238.00 | $10,125,809.00 | | | | | | | | | Design is being done by Jacobs Consulting Engineers. Public Hearing was held 07-29-10. The Let date is June 2012. Plans are currently at 70% complete. | http://maps.collincountytx.gov/rtrbond.html?rtr=20036 | | |  | | 20055 | TxDOT Dallas | On TxDOT Road System | | PGBT | | | Engineering and Construction | WIDEN PRESTON RD BRIDGE OVER PGBT TO PROVIDE 2 LEFT TURNS AND 1 DEDICATED SB RIGHT TURN LANE FOR PGBT ENTRANCE RAMPS. TxDOT CSJ# 0091-05-059 | | | $3,471,850.00 | $2,777,480.00 | | $694,370.00 | | | | | | | | Let date is Oct 2012. TxDOT is preparing LPAFA with the City of Plano. County Bond Project 07-060 with Plano has $600,000 available for local funding match. | http://maps.collincountytx.gov/rtrbond.html?rtr=20055 | | |  | | 20057 | TxDOT Dallas | On TxDOT Road System | | HEADQUARTERS ROAD, HEDGCOXE ROAD, SPRING CREEK PARKWAY | | | Engineering and Construction | ADD DUAL LEFT LANES AND DEDICATED RIGHT LANES. TxDOT CSJ# 0091-05-057 | | | $3,257,952.00 | $2,606,362.00 | | $651,590.00 | | | | | | | | Huitt-Zollars has started schematic and its sub Civil Associates has started environmental work. Jan. 2012 letting. | http://maps.collincountytx.gov/rtrbond.html?rtr=20057 | | |  | | 20076 | TxDOT Dallas | On TxDOT Road System | | FM 455 | Fannin County Line | | Engineering Only | Engineering only for widening of 2 lane rural highway to 4 lane divided roadway. TxDOT CSJ# 0549-03-021
| 2 | 4 | $6,250,000.00 | $5,000,000.00 | | $1,250,000.00 | | | | | | | | Collin County managed the Preliminary Engineering contract with LAN. The did the Schematic and ROW map in being developed. CC Bond Project #07-105. Final Design is not underway. Let date is 2020. | http://maps.collincountytx.gov/rtrbond.html?rtr=20076 | | |  | | 20083 | TxDOT Dallas | On TxDOT Road System | | FM 2551 | FM 1378 | | Engineering and Construction | Widen 2 lane rural to 4 lane (ultimate 6 lane) urban roadway. TxDOT CSJ# 2679-02-008 | 2 | 4 | $23,102,357.00 | | $18,138,686.00 | $4,963,671.00 | | | | | | | | Collin County is manging the preliminary Engineering, Bond Project #99-00-17 with Birkhoff, Hendricks and Carter doing preliminary Design and EA document. Had a Design meeting Sept 2, 2010 regarding the need for a Public Meeting and Schematic changes (shifting alignment to avoid existing waterline and easement). | http://maps.collincountytx.gov/rtrbond.html?rtr=20083 | | |  | | 20084 | TxDOT Dallas | On TxDOT Road System | | Outer Loop (CR 366) | Grayson County Line | | Engineering Only | ENGINEERING FOR RECONSTRUCTION OF MAINLANES FROM 4 TO 6 LANES; RECONSTRUCT 2 LANE FRONTAGE ROADS. txDOT CSj# 0047-14-053 | 4 | 6 | $6,250,000.00 | | $5,000,000.00 | $1,250,000.00 | | | | | | | | RTR funded for Preliminary Engineering only, no construction dollars. Design has not started. | http://maps.collincountytx.gov/rtrbond.html?rtr=20084 | | |  | | 20085 | TxDOT Dallas | On TxDOT Road System | | SH 121 | FM 455 | | Engineering Only | Engineering for reconstruction of mainlanes. TxDOT CSJ# 0047-04-022
| | | $2,800,000.00 | $2,000,000.00 | $240,000.00 | $560,000.00 | | | | | | | | RTR funded for Preliminary Engineering only, no construction dollars. Design has not began. | http://maps.collincountytx.gov/rtrbond.html?rtr=20085 | | |  | | 20091 | TxDOT Dallas | On TxDOT Road System | | Bois D' Arc | 1000' west of Lake Forest Dr. | | Engineering and Construction | Widen existing 4 lane divided urban arterial to a 6 lane divided cross section. TxDOT CSJ# 0135-02-046
| 4 | 6 | $9,865,371.00 | $7,892,297.00 | | $1,973,074.00 | | | | | | | | TxDOT in house design. Let Feb 2011, No ROW needed. TxDOT will be at 95% Plans mid Sept. 2010. | http://maps.collincountytx.gov/rtrbond.html?rtr=20091 | | |  | | 20092 | TxDOT Dallas | On TxDOT Road System | | 500' east of Custer Rd. (FM 2478) | 1000' east of Lake Forest Drive | | Engineering and Construction | Widen existing 5 lane undivided rural arterial to a 6 lane divided cross section.
TxDOT CSJ# 0135-02-045
| 5 | 6 | $26,891,421.00 | $22,389,527.00 | | $4,501,894.00 | | | | | | | | TxDOT is doing design in house. Project will be let in July 2011. No Right od Way is needed. Will submit 60% plans mid November 2010. | http://maps.collincountytx.gov/rtrbond.html?rtr=20092 | | |  | | 20095 | TxDOT Dallas | On TxDOT Road System | | Wilson Creek | US 380 | | Intellegent Transportation System | Extend existing ITS network. TxDOT CSJ# 0047-14-066
| | | $2,270,000.00 | $1,816,000.00 | | $454,000.00 | | | | | | | | Project was let in July 2010. Currently under construction.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20095 | | |  | | 20098 | TxDOT Dallas | On TxDOT Road System | | Exchange Pkwy | Eldorado Pkwy | | Intellegent Transportation System | US 75 From Exchange Parkway To Eldorado Parkway. TxDOT CSJ# 0047-06-144
| | | $2,960,000.00 | $2,368,000.00 | | $592,000.00 | | | | | | | | Project was let July 2010. Curretnly under construction.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20098 | | |  | | 20176 | TxDOT Dallas | On TxDOT Road System | | SH 5 | FM 455 | | Engineering and Construction | Widen 2 lane rural highway to 4 lane divided roadway. TxDOT CSJ# 0549-03-018 | 2 | 4 | $38,825,660.00 | | $31,580,528.00 | $7,245,132.00 | | | | | | | | SH 121 from US 75 to SH 5 will be widened with construction of US 75. Collin County Managed Prelim Design as Collin County Bond project # 07-105. LAN did Schematic and ROW map is being developed. TxDOT in house Final Design (District Office) working on 30% plans now. Let date Nov. 2012. Public Hearing will be scheduled in the near future.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20176 | | |  | | 20179 | TxDOT Dallas | On TxDOT Road System | | FM 455 | North Business 289C, North of Celina | | Engineering and Construction | WIDEN RURAL TWO LANE HIGHWAY TO SIX LANE URBAN DIVIDED. TxDOT CSJ: 0091-03-021 | 2 | 6 | $8,660,890.00 | | $6,928,712.00 | $1,732,178.00 | | | | | | | | Collin County managed Prelim. Engineering (LAN). TxDOT is doing in house Final Design (District Office). Let Date Oct 2011. Plans are near 30%. Public Hearing was held July 22nd, 2010. | http://maps.collincountytx.gov/rtrbond.html?rtr=20179 | | |  | | 20184 | TxDOT Dallas | On TxDOT Road System | | .929 miles west of CR 557 (Lake Lavon) | West of CR 608 in Farmersville, TX | | Construction Only | WIDEN EXISTING RURAL 2 LANE HIGHWAY TO 4 LANE DIVIDED. TxDOT CSJ# 0135-04-028 | 2 | 4 | $27,500,000.00 | $27,500,000.00 | | | | | | | | | | East Phase I, under construction. Expected completion is April 2011. | http://maps.collincountytx.gov/rtrbond.html?rtr=20184 | | |  | | 20197 | TxDOT Dallas | On TxDOT Road System | | Telephone Road (CR 275) | Melissa Road | | Engineering and Construction | RECONSTRUCT AND WIDEN 4 LANE TO 6 LANES AND 2 LANE FRONTAGE ROADS EACH DIRECTION.
TxDOT CSJ# 0047-14-068
| 4 | 6 | $47,351,374.00 | | $39,141,099.00 | $8,210,275.00 | | | | | | | | On going Selection process for Engineering Consultant.
| http://maps.collincountytx.gov/rtrbond.html?rtr=20197 | | |  | | 20198 | TxDOT Dallas | On TxDOT Road System | | Melissa Road | Outer Loop | | Engineering and Construction | RECONSTRUCT AND WIDEN 4 LANE TO 8 LANES AND 3 LANE FRONTAGE ROADS EACH DIRECTION.
TxDOT CSJ#0047-14-069 | 4 | 8 | $46,551,373.00 | | $38,341,098.00 | $8,210,275.00 | | | | | | | | Funding under question and review. | http://maps.collincountytx.gov/rtrbond.html?rtr=20198 | | |  | | 20201 | TxDOT Dallas | On TxDOT Road System | | FROM DALLAS COUNTY LINE | H 121 / SPUR 399 | | Engineering Only | HOV ACCESS RAMPS STUDY. TxDOT CSJ# 0047-06-145 | | | $500,000.00 | $500,000.00 | | | | | | | | | | | http://maps.collincountytx.gov/rtrbond.html?rtr=20201 | | |  | | 20202 | TxDOT Dallas | On TxDOT Road System | | US 380 Interchange | North of FM 1461 / BS 289D | | Engineering and Construction | RECONSTRUCT AND WIDEN TWO LANE RURAL HIGHWAY TO SIX LANE DIVIDED URBAN ROADWAY.
TxDOT CSJ# 0091-04-050
| 2 | 6 | $32,325,481.00 | | $25,647,878.00 | $6,677,603.00 | | | | | | | | Collin County Managed Preliminary Design (LAN). TxDOT is doing in house Final Design (District Office). Let Date July 2011. Final plans near 60%. Public Hearing was held July 22nd, 2010. | http://maps.collincountytx.gov/rtrbond.html?rtr=20202 | | |  | | 20203 | TxDOT Dallas | On TxDOT Road System | | North of FM 1461 / BS 289D | FM 455 in Celina | | Engineering and Construction | RECONSTRUCT AND WIDEN TWO LANE RURAL HIGHWAY TO SIX LANE DIVIDED URBAN ROADWAY.
TxDOT CSJ# 0091-04-055 | 2 | 6 | $34,750,000.00 | | $27,850,000.00 | | | | | | | | | Collin County Managed Preliminary Design (LAN). TxDOT is doing Final Design in house at the District Office. Let Date is July 2011. Plans are near 60%. Public Hearing was held July 22nd, 2010 | http://maps.collincountytx.gov/rtrbond.html?rtr=20203 | | |  | | 20204 | TxDOT Dallas | On TxDOT Road System | | at US 380 Interchange | | | Engineering and Construction | REPLACE OVERPASS AND APPROACHES. TxDOT CSJ# 0091-04-054 | | | $19,100,000.00 | | $16,000,000.00 | $3,100,000.00 | | | | | | | | LAN doing final design through Collin County. Let date is Nov 2011. Plans are in Austin and LAN is working on revisions now. On track for Nov 2011 letting. Public Hearing was held on July 15th, 2010. EA is clear. | http://maps.collincountytx.gov/rtrbond.html?rtr=20204 | | |  | | 20205 | TxDOT Dallas | On TxDOT Road System | | EAST OF FLOYD STREET | CR 698 (HUNT COUNTY LINE) | | Engineering and Construction | RECONSTRUCT EXISTING RURAL 2 LANE HIGHWAY TO 4 LANE DIVIDED. TxDOT CSJ# 0135-05-023 | 2 | 4 | $26,810,340.00 | $21,083,494.00 | | | | | | | | | | Other funds in the amount of $5,726,846 are available for this project. East Phase II. Project Let July 2010. Under delayed start waiting on utilities. Should start construction soon. | http://maps.collincountytx.gov/rtrbond.html?rtr=20205 | | |  | | 20206 | TxDOT Dallas | On TxDOT Road System | | WEST OF CR 608 IN FARMERSVILLE | EAST OF FLOYD ST | | Engineering and Construction | WIDEN EXISTING 2 LANE RURAL HIGHWAY TO 4 LANE DIVIDED, INCLUDING RAILROAD CROSSING. TxDOT CSJ# 0135-05-025. | 2 | 4 | $15,388,419.00 | $15,387,794.00 | | | | | | | | | | Other funds in the amount of $625 available for this project.
East Phase III, under design revision for Main St Bridge. On track for a July 2011 letting. | http://maps.collincountytx.gov/rtrbond.html?rtr=20206 | | |  | | 53114 | TxDOT Dallas | On TxDOT Road System | | South of Bloomdale | Telephone Rd. (CR 275) | | Construction Only | RECONSTRUCT AND WIDEN 4 LANES TO 8 LANES AND 3 LANE FRONTAGE ROADS EACH DIRECTION. TxDOT CSJ#0047-14-067
| 4 | 8 | $95,100,000.00 | $76,600,000.00 | | $18,500,000.00 | | | | | | | | Schematic under revision by TxDOT District Office. PS&E under design by Burns and Macdonald Engineering. Let date Nov 2011. | http://maps.collincountytx.gov/rtrbond.html?rtr=53114 | | |
|
|
|
|
|